Residential / Group Housing · 3 buildings · 148 unitsRERA P52100035183

Sparsh Aster

Completion was pushed back 4 months, to Apr 2027; no MahaRERA orders on record; 0% of its units are booked.

Kasar Amboli, Pune 412108 · Promoter: Shree Enterprises

DeliveryExtended 4 moPromised Dec 2026 · now due Apr 2027RegulatoryNo ordersNot in any MahaRERA list or order Deedo has readSales0% booked0 of 148 units · as the promoter reported to MahaRERA
Sparsh Aster project report cardPDF: delivery, regulatory orders, people on record, every tower and the registered deals — for your bank or lawyerSee what's inside · from ₹1,499

Completion was pushed back 4 months, to Apr 2027

  • This projectRegistered 10 May 2022, completion promised 31 Dec 2026, revised to 30 Apr 2027.

No extension certificate on record.

1 registration · Source: MahaRERA registration and extension certificates

Latest registered deeds

Sales, rentals and mortgages matched to this project · the free view shows a price band

No registered deeds matched to this project yet
Sales, resales, rentals and mortgages appear here once registered documents are matched to it by evidence.

3 buildings

Open a building to see every flat, floor by floor.

Floors and units from the registration certificate annexures and MahaRERA's project page.

Regulatory recordNone found

Deedo hasn't found this project's RERA number in any MahaRERA list or order it has read: deregistered, abeyance, NCLT, quarterly-report non-compliance, revoked, regulatory and suo motu orders.

Source: MahaRERA regulatory lists and orders, checked against each RERA number.

RERA registrationP52100035183
RegistrationRegisteredPromised completionRevised completionPromoterMahaRERA
P5210003518310 May 202231 Dec 202630 Apr 2027Shree EnterprisesProject page
Documents82

1 document held by Deedo, 81 filings listed on MahaRERA's project page

Registration certificate

Finance

  • PAN CardShree PAN.pdf · uploaded 11 Apr 2022Source

Legal

  • Legal Title report2_TC.pdf · uploaded 11 Apr 2022Source
  • Legal Title report2a_Annx.pdf · uploaded 11 Apr 2022Source
  • Legal Title report2b_Search.pdf · uploaded 11 Apr 2022Source
  • Declaration Form B8_Form B.pdf · uploaded 11 Apr 2022Source
  • Other16_Proposed Plan.PDF · uploaded 13 Apr 2022Source

Migrated

  • 1 PAN CardShree PAN.pdf · uploaded 11 Apr 2022Source
Show all 82 documentsShow fewer documents

Migrated

  • 1 Copy of the legal title report2_TC.pdf · uploaded 11 Apr 2022Source
  • 2 Copy of the legal title report2a_Annx.pdf · uploaded 11 Apr 2022Source
  • 3 Copy of the legal title report2b_Search.pdf · uploaded 11 Apr 2022Source
  • 1 Details of encumbrances3_NoEncumbrance.pdf · uploaded 11 Apr 2022Source
  • 1 Copy of Layout Approval (in case of layout)4_Layout.pdf · uploaded 11 Apr 2022Source
  • 1 Building Plan Approval / NA Order for plotted development5_1.pdf · uploaded 11 Apr 2022Source
  • 2 Building Plan Approval / NA Order for plotted development5_2.pdf · uploaded 11 Apr 2022Source
  • 3 Building Plan Approval / NA Order for plotted development5_3.pdf · uploaded 11 Apr 2022Source
  • 4 Building Plan Approval / NA Order for plotted development5_4.pdf · uploaded 11 Apr 2022Source
  • 5 Building Plan Approval / NA Order for plotted development5_5.pdf · uploaded 11 Apr 2022Source
  • 6 Building Plan Approval / NA Order for plotted development5_6.pdf · uploaded 11 Apr 2022Source
  • 7 Building Plan Approval / NA Order for plotted development5_7.pdf · uploaded 11 Apr 2022Source
  • 8 Building Plan Approval / NA Order for plotted development5_8.pdf · uploaded 11 Apr 2022Source
  • 9 Building Plan Approval / NA Order for plotted development5_9.pdf · uploaded 11 Apr 2022Source
  • 10 Building Plan Approval / NA Order for plotted development5_10.pdf · uploaded 11 Apr 2022Source
  • 11 Building Plan Approval / NA Order for plotted development5_11.pdf · uploaded 11 Apr 2022Source
  • 1 Declaration about Commencement Certificate7_CC Declaration.pdf · uploaded 11 Apr 2022Source
  • 1 Declaration in FORM B8_Form B.pdf · uploaded 11 Apr 2022Source
  • 1 Architect’s Certificate of Percentage of Completion of Work (Form 1)9_Ar.pdf · uploaded 11 Apr 2022Source
  • 1 Engineer’s Certificate on Cost Incurred on Project (Form 2)10_Er.pdf · uploaded 11 Apr 2022Source
  • 1 CERSAI details12_CERSAI.pdf · uploaded 11 Apr 2022Source
  • 1 CA Certificate on Project Cost & Fund withdrawal (Form 3)11_CA.pdf · uploaded 11 Apr 2022Source
  • 1 Proforma of Allotment letter13_Allotment.pdf · uploaded 13 Apr 2022Source
  • 2 Proforma of Allotment letter14_AfS.pdf · uploaded 13 Apr 2022Source
  • 1 Other16_Proposed Plan.PDF · uploaded 13 Apr 2022Source
  • 1 Commencement Certificates / NA Order for plotted development6_CC_Ar.pdf · uploaded 5 May 2022Source
  • 2 Commencement Certificates / NA Order for plotted development6_CC.pdf · uploaded 5 May 2022Source
  • 2 Architect’s Certificate of Percentage of Completion of Work (Form 1)202206_Ar.pdf · uploaded 7 Nov 2022Source
  • 3 Architect’s Certificate of Percentage of Completion of Work (Form 1)202209_Ar.pdf · uploaded 7 Nov 2022Source
  • 2 Engineer’s Certificate on Cost Incurred on Project (Form 2)202206_Er.pdf · uploaded 7 Nov 2022Source
  • 3 Engineer’s Certificate on Cost Incurred on Project (Form 2)202209_Er.pdf · uploaded 7 Nov 2022Source
  • 1 Architect’s Certificate of Percentage of Completion of Work (Form 1)Form1ASTER 30062024.pdf · uploaded 10 Dec 2024Source
  • 1 CA Certificate on Project Cost & Fund withdrawal (Form 3)ASTER FORM3 as on 300624.pdf · uploaded 10 Dec 2024Source
  • 1 Engineer’s Certificate on Cost Incurred on Project (Form 2)ENGINEERS CERTIFICATESPARSH PHASEIIASTERBUILDING NOA30092024.pdf · uploaded 10 Dec 2024Source
  • 1 Annual Audit Report of Statutory CA (Form 5) (FY 2023-24)From 5 Sparsh Aster 202324.pdf · uploaded 10 Dec 2024Source
  • Form 1Form 1.pdf · uploaded 1 Jul 2025Source
  • Form 2form 2.pdf · uploaded 1 Jul 2025Source
  • Form 3Form 3.pdf · uploaded 1 Jul 2025Source
  • Disclosure of Sold and Booked InventoryDISCLOSURE OF SOLD UNSOLD.pdf · uploaded 1 Jul 2025Source
  • Form 2A (FY 2024-2025)FORM 2A.pdf · uploaded 1 Jul 2025Source
  • Form 5 (FY 2023-2024)From 5.pdf · uploaded 1 Jul 2025Source
  • Withdrawal Update Form 1Sparsh Aster Form-1 June 2025.pdf · uploaded 14 Mar 2026Source
  • Withdrawal Update Form 2Sparsh Aster Form-2 Jun 2025.pdf · uploaded 14 Mar 2026Source
  • Withdrawal Update Form 3Sparsh Aster Form-3 June 2025.pdf · uploaded 14 Mar 2026Source
  • Withdrawal Update Form 1Sparsh Aster Form-1 Sep 2025.pdf · uploaded 18 Mar 2026Source
  • Withdrawal Update Form 2Sparsh Aster Form-2 Sep 2025.pdf · uploaded 18 Mar 2026Source
  • Withdrawal Update Form 3Sparsh Aster Form-3 Sep 2025.pdf · uploaded 18 Mar 2026Source
  • Withdrawal Update Form 1Sparsh Aster Form-1 Dec 2025.pdf · uploaded 28 Mar 2026Source
  • Withdrawal Update Form 2Sparsh Aster Form-2 Dec 2025.pdf · uploaded 28 Mar 2026Source
  • Withdrawal Update Form 3Sparsh Aster Form-3 Dec 2025.pdf · uploaded 28 Mar 2026Source
  • Form 5 (FY 2024-2025)Sparsh Aster Form-5 2024-25.pdf · uploaded 28 Mar 2026Source
  • Withdrawal Update Form 1FORM 1 ARCHITECT CERTIFICATE 31-03-2026.pdf · uploaded 9 Jul 2026Source
  • Withdrawal Update Form 2FORM 2 ENGINEER CERTIFICATE 31-03-2026.pdf · uploaded 9 Jul 2026Source
  • Withdrawal Update Form 3FORM 3 CA CERTIFICATE 31-03-2026.pdf · uploaded 9 Jul 2026Source
  • Form 2A (FY 2025-2026)FORM 2A 2025-2026.pdf · uploaded 9 Jul 2026Source
  • Withdrawal Update Form 1FORM 1 - 30-06-2026.pdf · uploaded 23 Jul 2026Source
  • Withdrawal Update Form 2FORM 2 - 30-06-2026.pdf · uploaded 23 Jul 2026Source
  • Withdrawal Update Form 3FORM 3 - 16-07-2026.pdf · uploaded 23 Jul 2026Source

Technical

  • Document4_Layout.pdf · uploaded 11 Apr 2022Source
  • Document5_1.pdf · uploaded 11 Apr 2022Source
  • Document5_2.pdf · uploaded 11 Apr 2022Source
  • Document5_3.pdf · uploaded 11 Apr 2022Source
  • Document5_4.pdf · uploaded 11 Apr 2022Source
  • Document5_5.pdf · uploaded 11 Apr 2022Source
  • Document5_6.pdf · uploaded 11 Apr 2022Source
  • Document5_7.pdf · uploaded 11 Apr 2022Source
  • Document5_8.pdf · uploaded 11 Apr 2022Source
  • Document5_9.pdf · uploaded 11 Apr 2022Source
  • Document5_10.pdf · uploaded 11 Apr 2022Source
  • Document5_11.pdf · uploaded 11 Apr 2022Source

Technical (Architect)

  • DocumentForm1ASTER 30062024.pdf · uploaded 10 Dec 2024Source
  • DocumentFORM 1 ARCHITECT CERTIFICATE 30-09-2026.pdf · uploaded 6 Oct 2026Source

Technical (Engineer)

  • DocumentENGINEERS CERTIFICATESPARSH PHASEIIASTERBUILDING NOA30092024.pdf · uploaded 10 Dec 2024Source
  • DocumentFORM 2 - 30-06-2026.pdf · uploaded 23 Jul 2026Source

Source: Certificates, orders and filings published by MahaRERA. Filings that can't be opened here are listed as they appear on MahaRERA's project page.

Land & approvals354, 360

As registered with MahaRERA and published on its project page

Project type
Residential / Group Housing
Status on MahaRERA
Certificate Signed
Unit types
1BHK, 1RK, 1.5BHK, 2BHK148 units in all
Address
354, 360, 370, Pune Poud Road, Kasar AmboliPIN 412108
Village
Kasar Amboli, Mulshi taluka
Designated bank account
85
Developed in phases
Yes

Survey, CTS, gat or plot numbers

354360370

Boundaries

North
Pune Poud Road
South
Gat No 357 358 359
East
Gat No 361 362
West
Gat No 213 356

Source: registration certificates and MahaRERA's project page, as stated there.

Units & parking148 units

0 of 148 units booked (0%), as the promoter reported to MahaRERA

1BHK · 124 units1RK · 1 unit1.5BHK · 2 units2BHK · 21 units
BuildingTypeCarpet areaUnitsBooked
Building A Wing A1BHK29.69 sq m · 320 sq ft100
Building A Wing A1BHK29.87 sq m · 322 sq ft100
Building A Wing A1BHK29.91 sq m · 322 sq ft100
Building A Wing A1BHK30.92 sq m · 333 sq ft50
Building A Wing A1BHK31.64 sq m · 341 sq ft50
Building A Wing A1BHK35.25 sq m · 379 sq ft70
Building A Wing A1RK22.88 sq m · 246 sq ft10
Building A Wing B1.5BHK43.71 sq m · 470 sq ft20
Show all 22 unit rowsShow fewer unit rows
BuildingTypeCarpet areaUnitsBooked
Building A Wing B1BHK33.14 sq m · 357 sq ft50
Building A Wing B1BHK33.16 sq m · 357 sq ft30
Building A Wing B1BHK33.18 sq m · 357 sq ft30
Building A Wing B1BHK33.67 sq m · 362 sq ft30
Building A Wing B1BHK33.69 sq m · 363 sq ft10
Building A Wing B1BHK33.78 sq m · 364 sq ft60
Building A Wing B1BHK36.16 sq m · 389 sq ft70
Building A Wing B2BHK49.22 sq m · 530 sq ft70
Building A Wing B2BHK49.66 sq m · 535 sq ft70
Building A Wing C1BHK29.78 sq m · 321 sq ft200
Building A Wing C1BHK29.9 sq m · 322 sq ft100
Building A Wing C1BHK31.61 sq m · 340 sq ft90
Building A Wing C1BHK36.19 sq m · 390 sq ft100
Building A Wing C2BHK49.52 sq m · 533 sq ft70

Source: MahaRERA project page, as the promoter filed it. Carpet areas are per unit.

Professionals8

Architects, engineers, chartered accountants and agents named on the registration

RoleNameRegistration no.
ArchitectNeha Jain—
ArchitectShinde Joshi & Associates—
Chartered accountantBrajesh—
Chartered accountantBrajesh Goyal & Associates—
Chartered accountantM G Suthar & Associates—
EngineerAjay P Patil—
EngineerAmar More—
EngineerAmol R Dhumal—

Source: MahaRERA project page. Contact details are not shown.

Data through13 Oct 2026SourcesMahaRERA project search · registration certificates · MahaRERA project pageData through is when MahaRERA's project page was last read.Methodology