Shantama Build Tec
Deedo IDDD-WVW5None of 4 registrations has reached its promised completion date yet.
Delivery record
2 of 4 registrations with dates moved or missed their RERA date · months late against the original promise
4 registrations with dates · Source: MahaRERA registration and extension certificates
Regulatory cases
No MahaRERA deregistration, abeyance, NCLT, revocation or other order names these registrations.
Projects
Delay is measured against the RERA proposed completion date on the registration certificate; * still open: the date has passed and MahaRERA shows no completion yet.
| Project | Locality | Status | Proposed | Revised | Delay |
|---|---|---|---|---|---|
| Happy CityP51500031654 | Georai | Certificate Signed | 31 Dec 2027 | 30 Apr 2028 | +4 mo |
| Aarambh Commercial SpacesP51500051954 | Georai | Completed | 31 Dec 2026 | — | On date |
| Happy City Phase 2P51500053100 | Georai Tanda | Active | 31 Dec 2028 | — | On date |
| Happy City Phase ThreePR1043032501926 | Georai | Certificate Signed | 31 Dec 2030 | 30 Apr 2031 | +4 mo |
Shantama Build Tec, in questions
Does Shantama Build Tec finish projects on time?
None of its 4 MahaRERA registrations has reached its promised completion date yet.
How many projects has Shantama Build Tec registered with MahaRERA?
4 projects under 4 MahaRERA registrations; 1 completed on MahaRERA.
Does Shantama Build Tec have MahaRERA regulatory cases?
No MahaRERA deregistration, abeyance, NCLT, revocation or other order names its registrations.