Sara Properties
Deedo IDDD-JER0Of 5 registrations whose promised date has arrived, 2 kept it (40%). The rest ran a median 12 mo late — longer than Maharashtra's 4 mo.
Delivery record
3 of 5 registrations with dates moved or missed their RERA date · months late against the original promise
5 registrations with dates · Source: MahaRERA registration and extension certificates
Regulatory cases
No MahaRERA deregistration, abeyance, NCLT, revocation or other order names these registrations.
Projects
Delay is measured against the RERA proposed completion date on the registration certificate; * still open: the date has passed and MahaRERA shows no completion yet.
| Project | Locality | Status | Proposed | Revised | Delay |
|---|---|---|---|---|---|
| Sara Parivartan - Sector B - Phase 1P51500001468 | Sawangi | Completed | 15 Aug 2019 | — | On date |
| Sara Samruddhi - Phase 1P51500013783 | Rotegaon | Certificate Signed | 31 Mar 2019 | 30 Sep 2020 | +18 mo |
| Sara Parivartan Sector B - Ph 2P51500016122 | Sawangi | Certificate Signed | 21 Apr 2022 | 20 Apr 2023 | +12 mo |
| SARA PARIVARTAN G - 12, 13, 14 type buildingP51500029499 | Sawangi | Certificate Signed | 31 Mar 2023 | 30 Mar 2024 | +12 mo |
| Sara Parivartan-Amenity Building-AP51500034773 | Sawangi | Certificate Signed | 31 Dec 2024 | 31 Dec 2024 | On date |
Sara Properties, in questions
Does Sara Properties finish projects on time?
Of 5 MahaRERA registrations whose promised completion date has arrived, 2 kept it (40%). The rest ran a median 12 mo late. Across Maharashtra, 73% kept their date.
How many projects has Sara Properties registered with MahaRERA?
5 projects under 5 MahaRERA registrations; 5 completed on MahaRERA.
Does Sara Properties have MahaRERA regulatory cases?
No MahaRERA deregistration, abeyance, NCLT, revocation or other order names its registrations.