Is this project on time and in good standing?

Projects: P + 11 digits (or two letters + 13 digits, like PR1260002500851). Agents: A + 11 digits.

RegisteredCompletion date passedMahaRERA status: Certificate Signed

P51500034773

Sara Parivartan-Amenity Building-A · Sawangi, Aurangabad · Sara Properties

Promised for 31 Dec 2024 — that date has passed and MahaRERA does not mark the project complete.

1 year and 10 months past the original promise today.

What to watch

Facts from the record. A flag is a reason to ask questions, not a verdict.

  • Risk: The latest completion date on record, 31 Dec 2024, has passed.
  • Clear: Completion date never extended.
  • Clear: Not on MahaRERA's deregistered, revoked, abeyance or insolvency lists.

Documents 1

Registration certificate28 Apr 2022View

Orders 0

No MahaRERA order or list names this number.

Questions about P51500034773

Is Sara Parivartan-Amenity Building-A delayed?

Yes. MahaRERA records a promised completion of 31 Dec 2024, which has passed, and the project is not marked complete.

How many extensions has it had?

Deedo holds 0 extension certificates for P51500034773.

Who is the promoter?

MahaRERA records Sara Properties as the promoter of P51500034773.

Is it on any MahaRERA regulatory list?

No MahaRERA order or list that Deedo holds names P51500034773.

Answers are generated from the record.

Data through25 Oct 2026, 02:20SourcesMahaRERA project register · registration and extension certificates · regulatory lists and ordersMethodology