Projects78 RERA registrations
Completed0as reported on MahaRERA project pages
Kept RERA date38%3 of 8 past their proposed date, not extended
Median delay+12 movs RERA proposed date · 5 extended
Regulatory cases1MahaRERA orders and lists
Projects
Delay is measured against the RERA proposed completion date on the registration certificate.
| Project | Locality | RERA year | Status | Proposed | Revised | Delay |
|---|---|---|---|---|---|---|
| Sanghvi S3 Ecocity WoodsP51900006575 | Mirabhayandar (M Corp.) | 2017 | Not reported | 30 Dec 2023 | 29 Dec 2024 | +12 months |
| Sanghvis Shri Parrsssva City 15-16P51700007140 | Atgaon | 2017 | Not reported | 31 Dec 2019 | 30 Jun 2026 | +78 months |
| Sanghvi EvanaP51900007455 | Ward Gsouth | 2017 | Not reported | 30 Dec 2021 | — | On date |
| Sanghvi S3 Ecocity OrchidP51900008323 | Mirabhayandar (M Corp.) | 2017 | Not reported | 30 Dec 2023 | 29 Dec 2024 | +12 months |
| Sanghvi Parsssva CityP51700009886 | Atgaon | 2017 | Not reported | 7 Mar 2025 | — | On date |
| Sanghvi HeightsP51900010060 | Mumbai City | 2017 | Not reported | 31 Dec 2018 | 31 Dec 2019 | +12 months |
| Sanghvi S3 Paradise - Phase 1P51900010903 | Mumbai City | 2017 | Not reported | 30 Dec 2021 | — | On date |
| Sanghvi HeightsP51900026345 | Mumbai City | 2020 | Not reported | 30 Jun 2024 | 30 Jun 2025 | +12 months |
Delivery timeline
RERA proposed completion vs the latest revised date, per registration.
Track record notes
- 3 of 8 registrations whose RERA proposed completion date has passed were never extended beyond it.
- Longest extension on record: 78 months, for Sanghvis Shri Parrsssva City 15-16 (P51700007140).
- MahaRERA records spell this promoter's name 3 ways; all of them are linked to this page through its registrations.
Regulatory cases across projects
- DeregisteredDeregistered: Sanghvis Shri Parrsssva City 15-16 · Sanghvis Shri Parrsssva City 15-16 · P51700007140
SourcesMahaRERA project pages · registration and extension certificates · regulatory lists and ordersPersonal details of promoters are not shown.Methodology