Salasar Estate Developers Llp
Deedo IDDD-8JVFOf 2 registrations whose promised date has arrived, 0 kept it (0%). The rest ran a median 48 mo late.
Delivery record
2 of 2 registrations with dates moved or missed their RERA date · months late against the original promise
2 registrations with dates · Source: MahaRERA registration and extension certificates
Regulatory cases
No MahaRERA deregistration, abeyance, NCLT, revocation or other order names these registrations.
Projects
Delay is measured against the RERA proposed completion date on the registration certificate; * still open: the date has passed and MahaRERA shows no completion yet.
| Project | Locality | Status | Proposed | Revised | Delay |
|---|---|---|---|---|---|
| Salasar WoodsP51700000177 | Bhayandar | Certificate Signed | 25 Dec 2022 | 24 Dec 2023 | +47 mo* |
| Salasar GreensP51700000586 | Bhayandar | Certificate Signed | 25 Dec 2022 | 31 Dec 2026 | +48 mo |
Salasar Estate Developers Llp, in questions
Does Salasar Estate Developers Llp finish projects on time?
Of 2 MahaRERA registrations whose promised completion date has arrived, 0 kept it (0%). The rest ran a median 48 mo late. Across Maharashtra, 73% kept their date.
How many projects has Salasar Estate Developers Llp registered with MahaRERA?
2 projects under 2 MahaRERA registrations; 0 completed on MahaRERA.
Does Salasar Estate Developers Llp have MahaRERA regulatory cases?
No MahaRERA deregistration, abeyance, NCLT, revocation or other order names its registrations.