Saiji Developers
Deedo IDDD-0CW9Of 2 registrations whose promised date has arrived, 1 kept it (50%). The rest ran a median 4 mo late — the same as Maharashtra's 4 mo.
Delivery record
3 of 4 registrations with dates moved or missed their RERA date · months late against the original promise
4 registrations with dates · Source: MahaRERA registration and extension certificates
Regulatory cases
No MahaRERA deregistration, abeyance, NCLT, revocation or other order names these registrations.
Projects
Delay is measured against the RERA proposed completion date on the registration certificate; * still open: the date has passed and MahaRERA shows no completion yet.
| Project | Locality | Status | Proposed | Revised | Delay |
|---|---|---|---|---|---|
| Marathe FortuneP51700008862 | Titwala | Certificate Signed | 31 Mar 2019 | 31 Mar 2019 | On date |
| Marathe ElenzaP51700010396 | Ulhasnagar (M Corp.) | Certificate Signed | 31 Jul 2026 | 30 Nov 2026 | +4 mo |
| Marathe TowerP51700022652 | Titwala | Certificate Signed | 31 Dec 2026 | 30 Apr 2027 | +4 mo |
| Marathe SapphireP51700032995 | Titwala | Certificate Signed | 31 Dec 2031 | 30 Apr 2032 | +4 mo |
Saiji Developers, in questions
Does Saiji Developers finish projects on time?
Of 2 MahaRERA registrations whose promised completion date has arrived, 1 kept it (50%). The rest ran a median 4 mo late. Across Maharashtra, 73% kept their date.
How many projects has Saiji Developers registered with MahaRERA?
4 projects under 4 MahaRERA registrations; 1 completed on MahaRERA.
Does Saiji Developers have MahaRERA regulatory cases?
No MahaRERA deregistration, abeyance, NCLT, revocation or other order names its registrations.