Skip to content

Compare projects side by side

Pick up to four MahaRERA-registered projects to see their registration, delivery, size and regulatory record next to each other.

Projects compared side by side
Titwala · Thane
Registration
RERA numbers
PromoterSaiji Developers
Status on MahaRERACertificate Signed
Registered on3 Feb 2022
Delivery
Promised completion31 Dec 2031
Revised completion30 Apr 2032
Delay vs RERA date+3 monthsrevised completion date
Extension certificates0
Size
Project land area—
Buildings on record1
Units185
Units booked00% of units
Regulatory
MahaRERA cases0
Documents on file1
Last checked on MahaRERA15 Oct 2026

Add a project

Search by project name, RERA number or building.

Add at least one more project to see which values are better.

Data through15 Oct 2026SourcesMahaRERA project search, registration and extension certificates, regulatory lists and orders, project pagesDelay counts months from the completion date promised at registration.Methodology