Sai Sahara Land Developers
Deedo IDDD-PMHVOf 4 registrations whose promised date has arrived, 4 kept it (100%).
Delivery record
None of 4 registrations with dates has moved or missed its RERA date
4 registrations with dates · Source: MahaRERA registration and extension certificates
Regulatory cases
No MahaRERA deregistration, abeyance, NCLT, revocation or other order names these registrations.
Projects
Delay is measured against the RERA proposed completion date on the registration certificate; * still open: the date has passed and MahaRERA shows no completion yet.
| Project | Locality | Status | Proposed | Revised | Delay |
|---|---|---|---|---|---|
| Shri Ram TownP50400018065 | Borgaon (Meghe) (Ct) | Certificate Signed | 28 Feb 2021 | 28 Feb 2021 | On date |
| Little Earth UnitP50400025364 | Pavnar | Completed | 30 Sep 2024 | — | On date |
| Little Earth UnitP50400025415 | Pavnar | Completed | 30 Jun 2024 | — | On date |
| Sai NagarP50400030354 | Borgaon (Meghe) (Ct) | Completed | 31 Mar 2024 | — | On date |
Sai Sahara Land Developers, in questions
Does Sai Sahara Land Developers finish projects on time?
Of 4 MahaRERA registrations whose promised completion date has arrived, 4 kept it (100%). Across Maharashtra, 73% kept their date.
How many projects has Sai Sahara Land Developers registered with MahaRERA?
3 projects under 4 MahaRERA registrations; 4 completed on MahaRERA.
Does Sai Sahara Land Developers have MahaRERA regulatory cases?
No MahaRERA deregistration, abeyance, NCLT, revocation or other order names its registrations.