Completed

P50400025364

Little Earth Unit · Pavnar, Wardha · Sai Sahara Land Developers

Promised for 30 Sep 2024; MahaRERA reports the project completed.

What to watch

Facts from the record. A flag is a reason to ask questions, not a verdict.

  • Clear: MahaRERA reports the project as completed.
  • Clear: Not on MahaRERA's deregistered, revoked, abeyance or insolvency lists.

Documents 13

Allotment letter28 Apr 2020View
Title report28 Apr 2020View
Form B28 Apr 2020View
Registration certificate8 Sep 2021View
Form 516 Feb 2023View
Form 516 Feb 2023View
Occupancy / completion certificate3 Apr 2023View
Form 413 Jul 2023View
Show all 13 documents
Form 511 Nov 2023View
Form 2A20 Nov 2023View
OtherView
Allotment letterView
Layout planView

Orders 0

No MahaRERA order or list names this number.

Questions about P50400025364

Is Little Earth Unit delayed?

MahaRERA reports it completed. Its promised completion date was 30 Sep 2024.

How many extensions has it had?

Deedo holds 0 extension certificates for P50400025364.

Who is the promoter?

MahaRERA records Sai Sahara Land Developers as the promoter of P50400025364.

Is it on any MahaRERA regulatory list?

No MahaRERA order or list that Deedo holds names P50400025364.

Answers are generated from the record.

Data through29 Oct 2026, 02:07SourcesMahaRERA project register · registration and extension certificates · regulatory lists and ordersReport a problemMethodology