Company or firm · first RERA registration 2024

Sai Asha Infra Edge City Llp

Deedo IDDD-E19D

None of 4 registrations has reached its promised completion date yet.

Projects14 RERA registrations
Kept RERA dateNone due yetMaharashtra: 73%
Median delayNone due yetwhen late · Maharashtra: 4 mo
First sales on record0registered first-sale deeds matched so far
Regulatory cases0none on record

Delivery record

None of 4 registrations with dates has moved or missed its RERA date

4 registrations with dates · Source: MahaRERA registration and extension certificates

Regulatory cases

No MahaRERA deregistration, abeyance, NCLT, revocation or other order names these registrations.

Projects

Delay is measured against the RERA proposed completion date on the registration certificate; * still open: the date has passed and MahaRERA shows no completion yet.

ProjectLocalityStatusProposedRevisedDelay
FloradaleP52100054577Kasar AmboliCertificate Signed31 Dec 202731 Dec 2027On date
FloradaleP52100054804Kasar AmboliCertificate Signed31 Dec 202731 Dec 2027On date
FloradaleP52100054853Kasar AmboliCertificate Signed31 Dec 202731 Dec 2027On date
FloradaleP52100055002Kasar AmboliCertificate Signed31 Dec 202731 Dec 2027On date

Sai Asha Infra Edge City Llp, in questions

Does Sai Asha Infra Edge City Llp finish projects on time?

None of its 4 MahaRERA registrations has reached its promised completion date yet.

How many projects has Sai Asha Infra Edge City Llp registered with MahaRERA?

1 project under 4 MahaRERA registrations; 2 completed on MahaRERA.

Does Sai Asha Infra Edge City Llp have MahaRERA regulatory cases?

No MahaRERA deregistration, abeyance, NCLT, revocation or other order names its registrations.

SourcesMahaRERA project pages · registration and extension certificates · regulatory lists and ordersPersonal details of promoters are not shown.Report a problemMethodology