RegisteredMahaRERA status: Certificate Signed
P52100054853
Floradale · Kasar Amboli, Pune · Sai Asha Infra Edge City Llp
Promised for 31 Dec 2027 and not extended so far.
1 year and 2 months to go until the promised date.
What to watch
Facts from the record. A flag is a reason to ask questions, not a verdict.
- ✓Clear: Completion date never extended.
- ✓Clear: Not on MahaRERA's deregistered, revoked, abeyance or insolvency lists.
Documents 2
Orders 0
No MahaRERA order or list names this number.
Questions about P52100054853
Is Floradale delayed?
Not so far. MahaRERA records a promised completion of 31 Dec 2027, which has not passed yet.
How many extensions has it had?
Deedo holds 0 extension certificates for P52100054853.
Who is the promoter?
MahaRERA records Sai Asha Infra Edge City Llp as the promoter of P52100054853.
Is it on any MahaRERA regulatory list?
No MahaRERA order or list that Deedo holds names P52100054853.