Skip to content
Individual promoter · first RERA registration 2022

Sachin Suryakant Bhamre

Deedo IDDD-VCET

Of 1 registration whose promised date has arrived, 1 kept it (100%).

Projects11 RERA registration
Kept RERA date100%Maharashtra: 73%
Median delay0 monone ran late
First sales on record0registered first-sale deeds matched so far
Regulatory cases1no insolvency

Delivery record

None of 1 registration with dates has moved or missed its RERA date

1 registration with dates · Source: MahaRERA registration and extension certificates

Regulatory cases

CaseProjectDate
Quarterly progress report not filedSunshine TowerQuarterly progress report not filed: SUNSHINE TOWERNot on record

Projects

Delay is measured against the RERA proposed completion date on the registration certificate; * still open: the date has passed and MahaRERA shows no completion yet.

ProjectLocalityStatusProposedRevisedDelay
Sunshine TowerP49900045331Amalner (M Cl)Completed31 Dec 2025—On date

Sachin Suryakant Bhamre, in questions

Does Sachin Suryakant Bhamre finish projects on time?

Of 1 MahaRERA registration whose promised completion date has arrived, 1 kept it (100%). Across Maharashtra, 73% kept their date.

How many projects has Sachin Suryakant Bhamre registered with MahaRERA?

1 project under 1 MahaRERA registration; 1 completed on MahaRERA.

Does Sachin Suryakant Bhamre have MahaRERA regulatory cases?

1 regulatory case name its registrations.

SourcesMahaRERA project pages · registration and extension certificates · regulatory lists and ordersPersonal details of promoters are not shown.Report a problemMethodology