Runwal Developers Ltd
Company or firm · 13 projects · 13 MahaRERA registrations
Also appears as RUNWAL DEVELOPERS LIMITED · Runwal Developers Pvt Ltd
13Projects13 RERA registrations
0Completedas reported on MahaRERA project pages
100%Kept RERA date3 of 3 past their proposed date, not extended
+4 moMedian delayvs RERA proposed date · 10 extended
0Regulatory casesMahaRERA orders and lists
Projects
Delay is measured against the RERA proposed completion date on the registration certificate.
| Project | Locality | RERA year | Status | Proposed | Revised | Delay |
|---|---|---|---|---|---|---|
| Runwal TimelessP51900005685 | Bhosari | 2017 | Certificate Signed | 30 Sep 2028 | 30 Jan 2029 | +4 months |
| Runwal Anthurium - ValentineP51800008477 | Kurla | 2017 | Certificate Signed | 31 Dec 2023 | 31 Dec 2023 | On date |
| Nirvana Part IP51900010100 | Lohgaon | 2017 | Certificate Signed | 30 Dec 2024 | 30 Dec 2024 | On date |
| Runwal R-SquareP51800022405 | Kurla | 2019 | Certificate Signed | 31 Dec 2026 | 30 Apr 2027 | +4 months |
| Codename Rare By RunwalP51800034594 | Andheri | 2022 | Certificate Signed | 30 Jun 2026 | 30 Jun 2026 | On date |
| ZenithP51700046734 | Thane (M Corp.) | 2022 | Certificate Signed | 30 Sep 2028 | 30 Jan 2029 | +4 months |
| 25HOURLIFE - Tower B1P51700048270 | Thane (M Corp.) | 2022 | Certificate Signed | 31 Dec 2029 | 30 Apr 2030 | +4 months |
| 25HOURLIFE - Tower C1P51700048278 | Thane (M Corp.) | 2022 | Certificate Signed | 31 Dec 2029 | 30 Apr 2030 | +4 months |
| 25HOURLIFE - Tower A1P51700053696 | Thane (M Corp.) | 2023 | Certificate Signed | 31 Dec 2030 | 30 Apr 2031 | +4 months |
| Runwal MalabarPR1170002502441 | Mumbai City | 2026 | Certificate Signed | 30 Jun 2032 | 30 Oct 2032 | +4 months |
| Runwal One-Tower D1PR1330002502798 | Chitalsar Manpada | 2026 | Certificate Signed | 30 Sep 2030 | 30 Jan 2031 | +4 months |
| Runwal One- Tower D2PR1330002502886 | Chitalsar Manpada | 2026 | Certificate Signed | 31 Jul 2031 | 30 Nov 2031 | +4 months |
| Runwal One-Tower EPR1330002503071 | Chitalsar Manpada | 2026 | Certificate Signed | 31 Jan 2031 | 31 May 2031 | +4 months |
Show all 13 registrationsShow fewer
Delivery timeline
RERA proposed completion vs the latest revised date, per registration.
Show all 13 registrations
Track record notes
- 3 of 3 registrations whose RERA proposed completion date has passed were never extended beyond it.
- Longest extension on record: 4 months, for Runwal Timeless (P51900005685).
- No MahaRERA regulatory order or list names these registrations.
- MahaRERA records spell this promoter's name 3 ways; all of them are linked to this page through its registrations.
Regulatory cases across projects
None on recordNo MahaRERA deregistration, abeyance, NCLT, revocation or other order names these registrations.
SourcesMahaRERA project pages · registration and extension certificates · regulatory lists and ordersPersonal details of promoters are not shown.Methodology