Company or firm · 15 projects · 15 MahaRERA registrations · 1 reported completed
15Projects15 RERA registrations
1Completedas reported on MahaRERA project pages
92%Kept RERA date12 of 13 past their proposed date, not extended
+0 moMedian delayvs RERA proposed date · 1 extended
0Regulatory casesMahaRERA orders and lists
Projects
Delay is measured against the RERA proposed completion date on the registration certificate.
| Project | Locality | RERA year | Status | Proposed | Revised | Delay |
|---|---|---|---|---|---|---|
| Trimurti Chsl Phase I - Upto 15th FloorP51800007589 | Kurla | 2017 | Not reported | 30 Dec 2021 | — | On date |
| Trimurti Chsl Phase II - 16th To 18th FloorP51800008089 | Kurla | 2017 | Not reported | 30 Dec 2023 | — | On date |
| Romell Diva Phase II - 17th To 20th FoorP51800014389 | Borivali | 2017 | Not reported | 30 Dec 2025 | — | On date |
| Romell Diva Phase III - 21st To 23rd FloorP51800014484 | Borivali | 2017 | Not reported | 30 Dec 2025 | — | On date |
| Romell Empress C Wing Phase I - Upto 13th FloorP51800018513 | Borivali | 2018 | Not reported | 30 Dec 2023 | — | On date |
| Romell Empress C Wing Phase II - 14th To 17th FloorP51800021923 | Borivali | 2019 | Completed | 30 Dec 2022 | — | On date |
| Romell RhythmP51800022142 | Borivali | 2019 | Not reported | 30 Dec 2023 | — | On date |
| Romell VasanthiP51800022238 | Kurla | 2019 | Not reported | 30 Dec 2024 | — | On date |
| Romell AllureP51800023445 | Borivali | 2019 | Not reported | 30 Dec 2023 | 4 Apr 2024 | +4 months |
| Romell Empress C Wing Phase III - 18th To 22nd FloorP51800025888 | Borivali | 2020 | Not reported | 30 Sep 2020 | — | On date |
| Romell EuphoriaP51800026583 | Borivali | 2020 | Not reported | 30 Jun 2023 | — | On date |
| Romell CornerstoneP51800032709 | Borivali | 2022 | Not reported | 31 Mar 2024 | — | On date |
| Romell SereneP51800034025 | Borivali | 2022 | Not reported | 31 Mar 2025 | — | On date |
| Romell ArianaPR1180002400010 | Eksar | 2024 | Not reported | 31 Dec 2028 | — | On date |
| Romell EspalierP51800079081 | Vileparle | 2025 | Not reported | 31 Dec 2030 | — | On date |
Show all 15 registrationsShow fewer
Delivery timeline
RERA proposed completion vs the latest revised date, per registration.
Show all 15 registrations
Track record notes
- 12 of 13 registrations whose RERA proposed completion date has passed were never extended beyond it.
- Longest extension on record: 4 months, for Romell Allure (P51800023445).
- No MahaRERA regulatory order or list names these registrations.
Regulatory cases across projects
None on recordNo MahaRERA deregistration, abeyance, NCLT, revocation or other order names these registrations.
SourcesMahaRERA project pages · registration and extension certificates · regulatory lists and ordersPersonal details of promoters are not shown.Methodology