RegisteredRevised date passed1 extensionMahaRERA status: Certificate Signed

P51800023445

Romell Allure · Borivali, Mumbai Suburban · Romell Real Estate Private Limited

Promised for 30 Dec 2023, extended once to 4 Apr 2024 — and that date has passed without the project marked complete on MahaRERA.

2 years and 10 months past the original promise today.

What to watch

Facts from the record. A flag is a reason to ask questions, not a verdict.

  • Caution: Completion date extended from 30 Dec 2023 to 4 Apr 2024 (1 extension certificate on record).
  • Risk: The latest completion date on record, 4 Apr 2024, has passed.
  • Clear: Not on MahaRERA's deregistered, revoked, abeyance or insolvency lists.

Documents 2

Registration certificate8 Sep 2021View
Extension certificate20 Sep 2023View

Orders 0

No MahaRERA order or list names this number.

Questions about P51800023445

Is Romell Allure delayed?

Yes. MahaRERA records a promised completion of 30 Dec 2023, revised to 4 Apr 2024, which has passed, and the project is not marked complete.

How many extensions has it had?

Deedo holds 1 extension certificate for P51800023445. The completion date moved from 30 Dec 2023 to 4 Apr 2024.

Who is the promoter?

MahaRERA records Romell Real Estate Private Limited as the promoter of P51800023445.

Is it on any MahaRERA regulatory list?

No MahaRERA order or list that Deedo holds names P51800023445.

Answers are generated from the record.

Data through28 Oct 2026, 02:25SourcesMahaRERA project register · registration and extension certificates · regulatory lists and ordersMethodology