Ravima Venture

Deedo IDDD-NE94

Of 3 registrations whose promised date has arrived, 2 kept it (67%). The rest ran a median 19 mo late.

Projects23 RERA registrations
Kept RERA date67%Maharashtra: 73%
Median delay19 mowhen late
First sales on record143registered first-sale deeds matched so far
Regulatory cases0none on record

Delivery record

1 of 3 registrations with dates moved or missed their RERA date · months late against the original promise

3 registrations with dates · Source: MahaRERA registration and extension certificates

Regulatory cases

No MahaRERA deregistration, abeyance, NCLT, revocation or other order names these registrations.

Projects

Delay is measured against the RERA proposed completion date on the registration certificate; * still open: the date has passed and MahaRERA shows no completion yet.

ProjectLocalityStatusProposedRevisedDelay
Newton Homes HadapsarP52100016517HadapsarCertificate Signed30 Apr 202430 Apr 2024On date
Newton Homes Hadapsar Phase-IP52100016522HadapsarCertificate Signed30 Apr 202330 Apr 2023On date
Newton Homes HadapsarP52100016523HadapsarCertificate Signed30 Apr 202531 Jul 2025+19 mo*

Ravima Venture, in questions

Does Ravima Venture finish projects on time?

Of 3 MahaRERA registrations whose promised completion date has arrived, 2 kept it (67%). The rest ran a median 19 mo late. Across Maharashtra, 73% kept their date.

How many projects has Ravima Venture registered with MahaRERA?

2 projects under 3 MahaRERA registrations; 2 completed on MahaRERA.

Does Ravima Venture have MahaRERA regulatory cases?

No MahaRERA deregistration, abeyance, NCLT, revocation or other order names its registrations.

SourcesMahaRERA project pages · registration and extension certificates · regulatory lists and ordersPersonal details of promoters are not shown.Report a problemMethodology