Randive Builders And Developers
Deedo IDDD-N2VFOf 4 registrations whose promised date has arrived, 0 kept it (0%). The rest ran a median 21 mo late.
Delivery record
5 of 7 registrations with dates moved or missed their RERA date · months late against the original promise
7 registrations with dates · Source: MahaRERA registration and extension certificates
Regulatory cases
No MahaRERA deregistration, abeyance, NCLT, revocation or other order names these registrations.
Projects
Delay is measured against the RERA proposed completion date on the registration certificate; * still open: the date has passed and MahaRERA shows no completion yet.
| Project | Locality | Status | Proposed | Revised | Delay |
|---|---|---|---|---|---|
| Dwarka AdrenoP53000003557 | Kolhapur (M Corp.) | Certificate Signed | 15 Oct 2020 | 31 Aug 2026 | +70 mo |
| Dwarka RavajiP53000005706 | Kolhapur (M Corp.) | Certificate Signed | 15 Feb 2021 | 24 Feb 2023 | +24 mo |
| NirvanaP53000020669 | Kolhapur (M Corp.) | Certificate Signed | 12 Feb 2025 | 12 Feb 2025 | +21 mo* |
| GrandstandP53000026678 | Kolhapur (M Corp.) | Certificate Signed | 30 Jun 2025 | 30 Jun 2025 | +17 mo* |
| Dwarka EuroP53000029821 | Uchgaon (Ct) | Certificate Signed | 31 Mar 2027 | 31 Jul 2027 | +4 mo |
| Dwarka Adreno Building BPR1151012601927 | Kolhapur (M Corp.) | Certificate Signed | 31 Dec 2030 | 31 Dec 2030 | On date |
| LegacyPM1150002602356 | Karvir | Not on record | 31 Dec 2031 | — | On date |
Randive Builders And Developers, in questions
Does Randive Builders And Developers finish projects on time?
Of 4 MahaRERA registrations whose promised completion date has arrived, 0 kept it (0%). The rest ran a median 21 mo late. Across Maharashtra, 73% kept their date.
How many projects has Randive Builders And Developers registered with MahaRERA?
7 projects under 7 MahaRERA registrations; 2 completed on MahaRERA.
Does Randive Builders And Developers have MahaRERA regulatory cases?
No MahaRERA deregistration, abeyance, NCLT, revocation or other order names its registrations.