Rameshawar Builders & Developers
Deedo IDDD-PGEDOf 4 registrations whose promised date has arrived, 2 kept it (50%). The rest ran a median 4 mo late.
Delivery record
4 of 6 registrations with dates moved or missed their RERA date · months late against the original promise
6 registrations with dates · Source: MahaRERA registration and extension certificates
Regulatory cases
No MahaRERA deregistration, abeyance, NCLT, revocation or other order names these registrations.
Projects
Delay is measured against the RERA proposed completion date on the registration certificate; * still open: the date has passed and MahaRERA shows no completion yet.
| Project | Locality | Status | Proposed | Revised | Delay |
|---|---|---|---|---|---|
| Rameshwar Park (Orchid, Iris & Rose)P51700008168 | Thane (M Corp.) | Certificate Signed | 31 Dec 2019 | 31 Dec 2019 | On date |
| Rameshwar Park - Daffodil AP51700014029 | Thane (M Corp.) | Certificate Signed | 30 Dec 2022 | 30 Dec 2022 | On date |
| Rameshwar Park - LilacP51700017242 | Thane (M Corp.) | Certificate Signed | 30 Dec 2021 | 28 Feb 2022 | +2 mo |
| Rameshwar Park - Daffodil BP51700021673 | Dawale | Certificate Signed | 30 Mar 2025 | 30 Mar 2025 | +20 mo* |
| Rameshwar Park - Daffodil CP51700079711 | Dawale | Certificate Signed | 31 Dec 2026 | 30 Apr 2027 | +4 mo |
| Rameshwar Park - A1 And A2P51700080694 | Thane (M Corp.) | Certificate Signed | 31 Dec 2027 | 30 Apr 2028 | +4 mo |
Rameshawar Builders & Developers, in questions
Does Rameshawar Builders & Developers finish projects on time?
Of 4 MahaRERA registrations whose promised completion date has arrived, 2 kept it (50%). The rest ran a median 4 mo late. Across Maharashtra, 73% kept their date.
How many projects has Rameshawar Builders & Developers registered with MahaRERA?
6 projects under 6 MahaRERA registrations; 3 completed on MahaRERA.
Does Rameshawar Builders & Developers have MahaRERA regulatory cases?
No MahaRERA deregistration, abeyance, NCLT, revocation or other order names its registrations.