Rameshwar Park - Lilac
Deedo IDDP-THN-EHXGMahaRERA shows it completed, after its date was pushed back 2 months; no MahaRERA orders on record; 81% of its units are booked.
Thane (M Corp.), Thane 400612 · by Rameshawar Builders & Developers · 50% of its projects kept the RERA date
Buying a flat here?
See every deed registered on it.
MahaRERA shows it completed, after its date was pushed back 2 months
- This projectRegistered 24 Jul 2018, completion promised 30 Dec 2021, revised to 28 Feb 2022.
1 extension certificate on record.
1 registration · Source: MahaRERA registration and extension certificates
Latest registered deeds
Sales, rentals and mortgages matched to this project · the free view shows a price band
The building
Open a building to see every flat, floor by floor.
Floors and units from the registration certificate annexures and MahaRERA's project page.
Regulatory recordNone found
Deedo hasn't found this project's RERA number in any MahaRERA list or order it has read: deregistered, abeyance, NCLT, quarterly-report non-compliance, revoked, regulatory and suo motu orders.
Source: MahaRERA regulatory lists and orders, checked against each RERA number.
RERA registrationP51700017242
| Registration | Registered | Promised completion | Revised completion | Promoter | MahaRERA |
|---|---|---|---|---|---|
| P51700017242 | 24 Jul 2018 | 30 Dec 2021 | 28 Feb 2022 | Rameshawar Builders & Developers | Project page |
Documents73
3 documents held by Deedo, 70 filings listed on MahaRERA's project page
Show all 73 documentsShow fewer documents
Migrated
- 1 Copy of the legal title reportTitle 208-8B.pdf · uploaded 12 Jul 2018Source
- 2 Copy of the legal title reportSearch Report-208-8B.pdf · uploaded 12 Jul 2018Source
- 1 Details of encumbrancesDeclaration of no encumbrances_1MB.pdf · uploaded 12 Jul 2018Source
- 1 Copy of Layout Approval (in case of layout)TMC 1_1MB.pdf · uploaded 12 Jul 2018Source
- 1 Building Plan Approval (IOD)TMC 2_1MB.pdf · uploaded 12 Jul 2018Source
- 1 Commencement Certificates / NA Order for plotted developmentCC_1mb.pdf · uploaded 12 Jul 2018Source
- 1 Declaration in FORM BForm B_1MB.pdf · uploaded 12 Jul 2018Source
- 3 Copy of the legal title reportClarification by Advocate.pdf · uploaded 14 Jul 2018Source
- 1 Certificates of Architect (Form 1)(Mandatory for only ongoing project)FORM 1_1MB.pdf · uploaded 18 Jul 2018Source
- 1 Certificates of Engineer (Form 2)(Mandatory for only ongoing project)Form 2_1mb.pdf · uploaded 18 Jul 2018Source
- 1 Certificates of CA (Form 3)Form 3 - Lilac.pdf · uploaded 18 Jul 2018Source
- 1 Proforma of Allotment letterTo whomsoever It May Concern.pdf · uploaded 18 Jul 2018Source
- 2 Proforma of Allotment letterUndertaking.pdf · uploaded 18 Jul 2018Source
- 1 Certificates of CA (Form 5)Lilac.pdf · uploaded 1 Aug 2019Source
- 2 Certificates of Architect (Form 1)(Mandatory for only ongoing project)1 From 1 Lilac 30092018.pdf · uploaded 23 Nov 2019Source
- 3 Certificates of Architect (Form 1)(Mandatory for only ongoing project)2 From 1 Lilac31122018.pdf · uploaded 23 Nov 2019Source
- 4 Certificates of Architect (Form 1)(Mandatory for only ongoing project)3 From 1 Lilac 31032019.pdf · uploaded 23 Nov 2019Source
- 5 Certificates of Architect (Form 1)(Mandatory for only ongoing project)4 From 1 Lilac 30062019.pdf · uploaded 23 Nov 2019Source
- 6 Certificates of Architect (Form 1)(Mandatory for only ongoing project)5 From 1 Lilac 30092019.pdf · uploaded 23 Nov 2019Source
- 2 Certificates of Engineer (Form 2)(Mandatory for only ongoing project)Form 2_Lilac_Sep 2018.pdf · uploaded 11 Feb 2020Source
- 3 Certificates of Engineer (Form 2)(Mandatory for only ongoing project)Form 2_Lilac_Dec 2018.pdf · uploaded 11 Feb 2020Source
- 4 Certificates of Engineer (Form 2)(Mandatory for only ongoing project)Form 2_Lilac_Mar 2019.pdf · uploaded 11 Feb 2020Source
- 5 Certificates of Engineer (Form 2)(Mandatory for only ongoing project)Form 2_Lilac_Jun 2019.pdf · uploaded 11 Feb 2020Source
- 6 Certificates of Engineer (Form 2)(Mandatory for only ongoing project)Form 2_Lilac_Sep 2019.pdf · uploaded 11 Feb 2020Source
- 2 Copy of Layout Approval (in case of layout)Layout_compressed.pdf · uploaded 17 Feb 2020Source
- 2 Building Plan Approval (IOD)Lilac Building Plan_compressed.pdf · uploaded 17 Feb 2020Source
- 2 Commencement Certificates / NA Order for plotted developmentRevised CC_compressed.pdf · uploaded 17 Feb 2020Source
- 1 Disclosure of sold/ booked inventoryDISCOLSURE OF SOLD BOOKED UNSOLD INVENTORY - LILAC-merged.pdf · uploaded 28 May 2021View
- 1 Engineers Certificate on Quality Assurance (Form 2A FY 2019-20)1 LILAC_30_6_2019.pdf · uploaded 31 Jul 2021Source
- 2 Engineers Certificate on Quality Assurance (Form 2A FY 2019-20)2 LILAC_30_9_2019.pdf · uploaded 31 Jul 2021Source
- 3 Engineers Certificate on Quality Assurance (Form 2A FY 2019-20)3 LILAC_31_12_2019-compressed.pdf · uploaded 31 Jul 2021Source
- 4 Engineers Certificate on Quality Assurance (Form 2A FY 2019-20)4 LILAC_31_3_2020.pdf · uploaded 31 Jul 2021Source
- 1 Engineers Certificate on Quality Assurance (Form 2A FY 2020-21)5 LILAC_30_6_2020.pdf · uploaded 31 Jul 2021Source
- 2 Engineers Certificate on Quality Assurance (Form 2A FY 2020-21)6 LILAC_30_9_2020.pdf · uploaded 31 Jul 2021Source
- 3 Engineers Certificate on Quality Assurance (Form 2A FY 2020-21)7 LILAC_31_12_2020.pdf · uploaded 31 Jul 2021Source
- 4 Engineers Certificate on Quality Assurance (Form 2A FY 2020-21)8 LILAC_31_3_2021.pdf · uploaded 31 Jul 2021Source
- 1 PAN CardRBD PAN CARD.pdf · uploaded 6 Aug 2021Source
- 7 Certificates of Architect (Form 1)(Mandatory for only ongoing project)6 Form1_Lilac_31_12_2019.pdf · uploaded 6 Aug 2021Source
- 8 Certificates of Architect (Form 1)(Mandatory for only ongoing project)7 Form1_Lilac_31_03_2020.pdf · uploaded 6 Aug 2021Source
- 9 Certificates of Architect (Form 1)(Mandatory for only ongoing project)8 Form1_Lilac_30_06_2020.pdf · uploaded 6 Aug 2021Source
- 10 Certificates of Architect (Form 1)(Mandatory for only ongoing project)9 Form1_lilac_30_09_2020.pdf · uploaded 6 Aug 2021Source
- 11 Certificates of Architect (Form 1)(Mandatory for only ongoing project)11 Form1_lilac_31_12_2020.pdf · uploaded 6 Aug 2021Source
- 12 Certificates of Architect (Form 1)(Mandatory for only ongoing project)11 Form1_Lilac_31_03_2021.pdf · uploaded 6 Aug 2021Source
- 7 Certificates of Engineer (Form 2)(Mandatory for only ongoing project)6 Lilac_31_12_2019.pdf · uploaded 6 Aug 2021Source
- 8 Certificates of Engineer (Form 2)(Mandatory for only ongoing project)7 LILAC_31_3_2020.pdf · uploaded 6 Aug 2021Source
- 9 Certificates of Engineer (Form 2)(Mandatory for only ongoing project)8 LILAC_30_6_2020.pdf · uploaded 6 Aug 2021Source
- 10 Certificates of Engineer (Form 2)(Mandatory for only ongoing project)9 LILAC_30_9_2020.pdf · uploaded 6 Aug 2021Source
- 11 Certificates of Engineer (Form 2)(Mandatory for only ongoing project)10 LILAC_31_12_2020.pdf · uploaded 6 Aug 2021Source
- 12 Certificates of Engineer (Form 2)(Mandatory for only ongoing project)11 LILAC_31_3_2021.pdf · uploaded 6 Aug 2021Source
- 13 Certificates of Architect (Form 1)(Mandatory for only ongoing project)13 FORM 1 _LILAC_30_06_2021_compressed.pdf · uploaded 13 Nov 2021Source
- 14 Certificates of Architect (Form 1)(Mandatory for only ongoing project)14 FORM 1 _LILAC_30_09_2021_compressed.pdf · uploaded 13 Nov 2021Source
- 1 Annual Audit Report of Statutory CA (Form 5) (FY 2018-19)Form 5 1819_Signed Compressed.pdf · uploaded 12 Jan 2022Source
- 1 Annual Audit Report of Statutory CA (Form 5) (FY 2019-20)Form 5 2019-20_Signed COMPRESSED.pdf · uploaded 12 Jan 2022Source
- 1 Annual Audit Report of Statutory CA (Form 5) (FY 2020-21)Form 5 2021_Signed.pdf · uploaded 12 Jan 2022Source
- 1 Declaration about Commencement CertificateDeclaration about CC.pdf · uploaded 13 Jan 2022Source
- 1 Occupancy Certificate/ Completion Certificate/ Architect's certificate of completion for plotted developmentCert_ART_43511_LILAC-OC -ORIIGINAL.pdf · uploaded 2 Mar 2022Source
- 15 Certificates of Architect (Form 1)(Mandatory for only ongoing project)15 FORM 1 _LILAC_31_12_2021.pdf · uploaded 21 May 2022Source
- 1 Architect’s Certificate on Completion of Project (Form 4)Form 4_Lilac.pdf · uploaded 21 May 2022Source
- 1 Status of Formation of Legal Entity (Society/Co Op etc.)LILAC Society Registration.pdf · uploaded 27 Sep 2023Source
Technical
Technical (Architect)
- Document15 FORM 1 _LILAC_31_12_2021.pdf · uploaded 21 May 2022Source
Technical (Engineer)
- Document11 LILAC_31_3_2021.pdf · uploaded 6 Aug 2021Source
Source: Certificates, orders and filings published by MahaRERA. Filings that can't be opened here are listed as they appear on MahaRERA's project page.
Land & approvalsLand parcel 208/8A
As registered with MahaRERA and published on its project page
- Project type
- Residential / Group Housing
- Status on MahaRERA
- Certificate Signed
- Unit types
- 1BHK, Shop52 units in all
- Address
- 208/8A, Diva Shil Road, Dawale Gaon, Near Sai Baba MandirPIN 400612
- Village
- Thane (M Corp.), Thane taluka
- Location
- 19.16279, 73.04623
- Land area for this project
- 1,000 sq m (10,764 sq ft)
- Permissible built-up area
- 1,620 sq m (17,438 sq ft)
- Sanctioned built-up area
- 868 sq m (9,343 sq ft)
- Designated bank account
- 117
- Developed in phases
- No
Survey, CTS, gat or plot numbers
Land as published on MahaRERA's project page
208/8A
Boundaries
- North
- 6 M WI Existing Road
- South
- Survey No 208 Hissa No 7
- East
- Survey No 208 Hissa No 6
- West
- Survey No 208 Hissa No 8B
Source: registration certificates and MahaRERA's project page, as stated there.
Units & parking52 units
42 of 52 units booked (81%), as the promoter reported to MahaRERA
| Type | Carpet area | Units | Booked |
|---|---|---|---|
| 1BHK | 29.91 sq m · 322 sq ft | 11 | 6 |
| 1BHK | 30.19 sq m · 325 sq ft | 6 | 5 |
| 1BHK | 30.66 sq m · 330 sq ft | 7 | 7 |
| 1BHK | 31.4 sq m · 338 sq ft | 7 | 6 |
| 1BHK | 31.96 sq m · 344 sq ft | 7 | 6 |
| 1BHK | 32.33 sq m · 348 sq ft | 6 | 4 |
| Shop | 9.29 sq m · 100 sq ft | 1 | 1 |
| Shop | 9.66 sq m · 104 sq ft | 1 | 1 |
Show all 13 unit rowsShow fewer unit rows
| Type | Carpet area | Units | Booked |
|---|---|---|---|
| Shop | 9.94 sq m · 107 sq ft | 1 | 1 |
| Shop | 12.91 sq m · 139 sq ft | 1 | 1 |
| Shop | 13.1 sq m · 141 sq ft | 1 | 1 |
| Shop | 13.66 sq m · 147 sq ft | 1 | 1 |
| Shop | 16.26 sq m · 175 sq ft | 2 | 2 |
Source: MahaRERA project page, as the promoter filed it. Carpet areas are per unit.
Professionals2
Architects, engineers, chartered accountants and agents named on the registration
| Role | Name | Registration no. |
|---|---|---|
| Architect | Sameer S Lotke And Associates | — |
| Engineer | Pankaj Kumar | — |
Source: MahaRERA project page. Contact details are not shown.