Individual promoter · first RERA registration 2026
Rajesh Kashinath Prachande
Deedo IDDD-SPG3None of 1 registration has reached its promised completion date yet.
Projects11 RERA registration
Kept RERA dateNone due yetMaharashtra: 73%
Median delayNone due yetwhen late · Maharashtra: 4 mo
First sales on record0registered first-sale deeds matched so far
Regulatory cases0none on record
Delivery record
None of 1 registration with dates has moved or missed its RERA date
1 registration with dates · Source: MahaRERA registration and extension certificates
Regulatory cases
No MahaRERA deregistration, abeyance, NCLT, revocation or other order names these registrations.
Projects
Delay is measured against the RERA proposed completion date on the registration certificate; * still open: the date has passed and MahaRERA shows no completion yet.
| Project | Locality | Status | Proposed | Revised | Delay |
|---|---|---|---|---|---|
| Rita EmpirePR1320002502449 | Neharu Nagar | Certificate Signed | 31 Dec 2030 | 31 Dec 2030 | On date |
Rajesh Kashinath Prachande, in questions
Does Rajesh Kashinath Prachande finish projects on time?
None of its 1 MahaRERA registration has reached its promised completion date yet.
How many projects has Rajesh Kashinath Prachande registered with MahaRERA?
1 project under 1 MahaRERA registration; 0 completed on MahaRERA.
Does Rajesh Kashinath Prachande have MahaRERA regulatory cases?
No MahaRERA deregistration, abeyance, NCLT, revocation or other order names its registrations.
SourcesMahaRERA project pages · registration and extension certificates · regulatory lists and ordersPersonal details of promoters are not shown.Report a problemMethodology