Rajendra Sukhadev Mirgane

Deedo IDDD-1R2M

Of 2 registrations whose promised date has arrived, 1 kept it (50%). The rest ran a median 51 mo late.

Projects33 RERA registrations
Kept RERA date50%Maharashtra: 73%
Median delay51 mowhen late
First sales on record0registered first-sale deeds matched so far
Regulatory cases0none on record

Delivery record

1 of 3 registrations with dates moved or missed their RERA date · months late against the original promise

3 registrations with dates · Source: MahaRERA registration and extension certificates

Regulatory cases

No MahaRERA deregistration, abeyance, NCLT, revocation or other order names these registrations.

Projects

Delay is measured against the RERA proposed completion date on the registration certificate; * still open: the date has passed and MahaRERA shows no completion yet.

ProjectLocalityStatusProposedRevisedDelay
Rsm Heights C TowerP52600005087BarshiCertificate Signed31 Dec 202630 Jun 2024On date
Sukhadev Nagar Phase I Part 1P52600006417BarshiCertificate Signed30 Jun 202330 Jun 2023On date
RSM Heights E PhaseP52600017608BarshiCertificate Signed16 Aug 202216 Aug 2022+51 mo*

Rajendra Sukhadev Mirgane, in questions

Does Rajendra Sukhadev Mirgane finish projects on time?

Of 2 MahaRERA registrations whose promised completion date has arrived, 1 kept it (50%). The rest ran a median 51 mo late. Across Maharashtra, 73% kept their date.

How many projects has Rajendra Sukhadev Mirgane registered with MahaRERA?

3 projects under 3 MahaRERA registrations; 1 completed on MahaRERA.

Does Rajendra Sukhadev Mirgane have MahaRERA regulatory cases?

No MahaRERA deregistration, abeyance, NCLT, revocation or other order names its registrations.

SourcesMahaRERA project pages · registration and extension certificates · regulatory lists and ordersPersonal details of promoters are not shown.Report a problemMethodology