Company or firm · 3 projects · 3 MahaRERA registrations

Projects33 RERA registrations
Completed0as reported on MahaRERA project pages
Kept RERA date100%2 of 2 past their proposed date, not extended
Median delay+0 movs RERA proposed date · 0 extended
Regulatory cases0MahaRERA orders and lists

Projects

Delay is measured against the RERA proposed completion date on the registration certificate.

ProjectLocalityRERA yearStatusProposedRevisedDelay
KingstownP52100023079Chandkhed2019Not reported30 Mar 2025—On date
Top Towers - AP52100034929Wakad2022Not reported30 Jun 2026—On date
Top Towers - BP52100077165Wakad2024Not reported31 Jul 2027—On date

Delivery timeline

RERA proposed completion vs the latest revised date, per registration.

  • KingstownOn date
  • Top Towers - AOn date
  • Top Towers - BOn date

Track record notes

  • 2 of 2 registrations whose RERA proposed completion date has passed were never extended beyond it.
  • No MahaRERA regulatory order or list names these registrations.

Regulatory cases across projects

None on recordNo MahaRERA deregistration, abeyance, NCLT, revocation or other order names these registrations.
SourcesMahaRERA project pages · registration and extension certificates · regulatory lists and ordersPersonal details of promoters are not shown.Methodology