Rachana Construction Co. (Nagpur) Pvt. Ltd

Company or firm · 7 projects · 7 MahaRERA registrations · 1 reported completed

Also appears as Rachana Construction Co. (Nagpur) Pvt. Ltd.

Projects77 RERA registrations
Completed1as reported on MahaRERA project pages
Kept RERA date20%1 of 5 past their proposed date, not extended
Median delay+10 movs RERA proposed date · 4 extended
Regulatory cases0MahaRERA orders and lists

Projects

Delay is measured against the RERA proposed completion date on the registration certificate.

ProjectLocalityRERA yearStatusProposedRevisedDelay
Rachana Sahira Wing AP50500001307Nagpur (M Corp.)2017Not reported31 Oct 201831 Oct 2019+12 months
Rachana 24 CaratP50500002136Nagpur (M Corp.)2017Not reported26 Aug 201826 Feb 2021+30 months
Rachana Madhukosh Wing CP50500015593Nagpur (M Corp.)2018Completed30 Jun 201930 Dec 2020+18 months
Rachana Sahira Wing BP50500020517Nagpur (M Corp.)2019Not reported30 Sep 2022—On date
Rachana EkaaP50500034119Nagpur (M Corp.)2022Not reported31 Mar 202431 Jan 2025+10 months
Rachana Ekaa-2P50500055492Nagpur (M Corp.)2024Not reported31 Dec 2026—On date
Rachana Vivantam (Tower B)PR1190002600532Hazari Pahad2026Not reported31 Dec 2029—On date

Delivery timeline

RERA proposed completion vs the latest revised date, per registration.

  • Rachana Sahira Wing A+12 mo
  • Rachana 24 Carat+30 mo
  • Rachana Madhukosh Wing C+18 mo
  • Rachana Sahira Wing BOn date
  • Rachana Ekaa+10 mo
  • Rachana Ekaa-2On date
  • Rachana Vivantam (Tower B)On date

Track record notes

  • 1 of 5 registrations whose RERA proposed completion date has passed was never extended beyond it.
  • Longest extension on record: 30 months, for Rachana 24 Carat (P50500002136).
  • No MahaRERA regulatory order or list names these registrations.
  • MahaRERA records spell this promoter's name 2 ways; all of them are linked to this page through its registrations.

Regulatory cases across projects

None on recordNo MahaRERA deregistration, abeyance, NCLT, revocation or other order names these registrations.