Rachana Madhukosh Wing C

Completed

Nagpur (M Corp.), Nagpur 440022 |Promoter: Rachana construction Co. (Nagpur) Pvt. Ltd.

Residential / Group HousingRERAP50500015593
12 Mar 2018Registered with MahaRERA
30 Jun 2019Promised completion
30 Dec 2020Revised completionPushed back 1 year and 6 months
1Building
0MahaRERA listings and ordersNone found

Project summary

As registered with MahaRERA and published on its project page

Project type
Residential / Group Housing
Status on MahaRERA
Completed
Buildings
1
Land area for this project
6,017 sq m (64,769 sq ft)
Permissible built-up area
8,830 sq m (95,049 sq ft)
Sanctioned built-up area
8,830 sq m (95,049 sq ft)
Recreational open space
903 sq m (9,715 sq ft)
Address
Plot no 1, 2, 3, 4, 5, KH No - 99/2, Mouza - Bhamti, Near London street, BhamtiPIN 440022
Litigation declared by promoter
None declared

Location

Coordinates as published by MahaRERA

View on OpenStreetMap 18.59696, 73.77481
Rachana Madhukosh Wing C is at latitude 18.59696, longitude 73.77481.

Latest registered deals

No registered transactions matched to this project yetSales, resales and rentals appear here once registered documents from authorised IGR feeds are matched to this project.

Completion timeline

Registration date, the completion date promised at registration, and any extension since

Completion pushed back 1 year and 6 months

The latest completion date on record passed 5 years and 10 months ago.

Registered
12 Mar 2018
Promised
30 Jun 2019
Revised
30 Dec 2020

RERA registration

RegistrationRegisteredPromised completionRevised completionPromoterMahaRERA
P5050001559312 Mar 201830 Jun 201930 Dec 2020Rachana construction Co. (Nagpur) Pvt. Ltd.Project page

1 building

Buildings and wings named in the registration

BuildingSanctioned floorsUnits
Wing C7—

Source: registration certificate annexures and MahaRERA's project page. “Floors with CC” counts floors covered by a commencement certificate.

Units and parking

0 units registered

Parking

TypeTwo-wheelerFour-wheelerBusVisitorTotal
Closed/Covered000011
Open Space00006

Source: MahaRERA project page, as the promoter filed it. Carpet areas are per unit.

Documents

5 documents held by Deedo, 31 filings listed on MahaRERA's project page

Registration certificate

Form 1s

Extension certificate

Document library

  • Copy of the legal title reportSEARCH REPORT.pdf · uploaded 20 Feb 2018Source
  • Declaration in FORM BFORM 4B.pdf · uploaded 20 Feb 2018Source
  • Proforma of Allotment letterprofarma agr to sell and allotment.pdf · uploaded 20 Feb 2018Source
  • OtherDECLARATION.pdf · uploaded 20 Feb 2018Source
  • Details of encumbrancesEncumbrance certificate.pdf · uploaded 20 Feb 2018Source
  • Copy of Layout Approval (in case of layout)Plan 1.pdf · uploaded 8 Mar 2018Source
  • Building Plan Approval (IOD)Plan 1.pdf · uploaded 8 Mar 2018Source
  • Commencement Certificates / NA Order for plotted developmentcommencement cert.pdf · uploaded 8 Mar 2018Source
  • Building Plan Approval (IOD)plan 2.pdf · uploaded 8 Mar 2018Source
  • Certificates of CA (Form 5)madhukosh III.pdf · uploaded 4 Oct 2018Source
  • Certificates of Architect (Form 1)(Mandatory for only ongoing project)Form 1 Mar 18.pdf · uploaded 2 Feb 2019Source
  • Certificates of Architect (Form 1)(Mandatory for only ongoing project)Arch Mdhk C March 18.pdf · uploaded 2 Feb 2019Source
  • Certificates of Architect (Form 1)(Mandatory for only ongoing project)Arch Mdhk Sept 18.pdf · uploaded 2 Feb 2019Source
  • Certificates of Engineer (Form 2)(Mandatory for only ongoing project)Engg Mdhk March 18.pdf · uploaded 2 Feb 2019Source
  • Certificates of Engineer (Form 2)(Mandatory for only ongoing project)Engg Mdhk Jun 18.pdf · uploaded 2 Feb 2019Source
  • Certificates of Engineer (Form 2)(Mandatory for only ongoing project)Engg Mdhk Sept 18.pdf · uploaded 2 Feb 2019Source
  • Architect’s Certificate on Completion of Project (Form 4)Form 4 Mdhk C.pdf · uploaded 6 Sep 2019Source
  • Occupancy Certificate/ Completion Certificate/ Architect's certificate of completion for plotted developmentOC Mdhk C.pdf · uploaded 6 Sep 2019Source
  • Certificates of Architect (Form 1)(Mandatory for only ongoing project)M Form 1 301218.pdf · uploaded 14 Sep 2019View
  • Certificates of Architect (Form 1)(Mandatory for only ongoing project)M Form 1 300319.pdf · uploaded 14 Sep 2019View
  • Certificates of Architect (Form 1)(Mandatory for only ongoing project)M Form 1300619.pdf · uploaded 14 Sep 2019View
  • Certificates of CA (Form 5)Madhukosh C Form 5.pdf · uploaded 30 Sep 2019Source
  • Othermadhukosh OC.pdf · uploaded 6 Mar 2020Source

Promoter documents

  • Legal Title reportSEARCH REPORT.pdf · uploaded 20 Feb 2018Source
  • Declaration Form BFORM 4B.pdf · uploaded 20 Feb 2018Source

Technical documents

  • Layout ApprovalPlan 1.pdfSource
  • Building Plan ApprovalPlan 1.pdfSource
  • Building Plan Approvalplan 2.pdfSource

Other legal documents

Proforma allotment letter

  • Proforma allotment letterprofarma agr to sell and allotment.pdfSource

Source: Certificates, orders and filings published by MahaRERA. Filings that can't be opened here are listed as they appear on MahaRERA's project page.

Regulatory record

Deedo hasn't found this project's RERA number in any MahaRERA list or order it has read: deregistered, abeyance, NCLT, quarterly-report non-compliance, revoked, regulatory and suo motu orders.

Source: MahaRERA regulatory lists and orders, checked against each RERA number.

Land

In Nagpur (M Corp.), Nagpur (Urban) taluka

Survey, CTS, gat or plot numbers

2345KH No 99/2Plot no 1

As published on MahaRERA's project page

Plot no 1,2,3,4,5 , KH No - 99/2 , Mouza - Bhamti

Boundaries

North
Other layout
South
9 M Road
East
Other layout
West
9 M Road

Source: registration certificates and MahaRERA's project page, as stated there.

Professionals

Architects, engineers, chartered accountants and agents named on the registration

RoleNameRegistration no.
ArchitectUlhas mude & Associates—
EngineerP T Mase & Associates—
OtherZopate Electrical consultants pvt ltd—

Source: MahaRERA project page. Contact details are not shown.

Data through9 Oct 2026SourcesMahaRERA project search · registration certificates · MahaRERA project pageData through is when MahaRERA's project page was last read.Methodology