Company or firm · 2 projects · 2 MahaRERA registrations

Also appears as M/S PREETAM ASSOCIATES

Projects22 RERA registrations
Completed0as reported on MahaRERA project pages
Kept RERA date100%2 of 2 past their proposed date, not extended
Median delay+0 movs RERA proposed date · 0 extended
Regulatory cases0MahaRERA orders and lists

Projects

Delay is measured against the RERA proposed completion date on the registration certificate.

ProjectLocalityRERA yearStatusProposedRevisedDelay
Smurti AnandP52100026569Pimpri Chinchawad (M Corp.)2020Not reported15 May 2023—On date
Sukhmani NiwasP52100048054Pimpri Chinchawad (M Corp.)2022Not reported31 Mar 2024—On date

Delivery timeline

RERA proposed completion vs the latest revised date, per registration.

  • Smurti AnandOn date
  • Sukhmani NiwasOn date

Track record notes

  • 2 of 2 registrations whose RERA proposed completion date has passed were never extended beyond it.
  • No MahaRERA regulatory order or list names these registrations.
  • MahaRERA records spell this promoter's name 2 ways; all of them are linked to this page through its registrations.

Regulatory cases across projects

None on recordNo MahaRERA deregistration, abeyance, NCLT, revocation or other order names these registrations.
SourcesMahaRERA project pages · registration and extension certificates · regulatory lists and ordersPersonal details of promoters are not shown.Methodology