P52100026569
Smurti Anand · Pimpri Chinchawad (M Corp.), Pune · Preetam Associates
Promised for 15 May 2023 — that date has passed and MahaRERA does not mark the project complete.
3 years and 5 months past the original promise today.
What to watch
Facts from the record. A flag is a reason to ask questions, not a verdict.
- !Risk: The latest completion date on record, 15 May 2023, has passed.
- ✓Clear: Completion date never extended.
- ✓Clear: Not on MahaRERA's deregistered, revoked, abeyance or insolvency lists.
Documents 1
Orders 0
No MahaRERA order or list names this number.
Questions about P52100026569
Is Smurti Anand delayed?
Yes. MahaRERA records a promised completion of 15 May 2023, which has passed, and the project is not marked complete.
How many extensions has it had?
Deedo holds 0 extension certificates for P52100026569.
Who is the promoter?
MahaRERA records Preetam Associates as the promoter of P52100026569.
Is it on any MahaRERA regulatory list?
No MahaRERA order or list that Deedo holds names P52100026569.
Answers are generated from the record.