Of 6 registrations whose promised date has arrived, 1 kept it (17%). The rest ran a median 24 mo late.

Projects66 RERA registrations
Kept RERA date17%Maharashtra: 73%
Median delay24 mowhen late
First sales on record0registered first-sale deeds matched so far
Regulatory cases0none on record

Delivery record

5 of 6 registrations with dates moved or missed their RERA date · months late against the original promise

6 registrations with dates · Source: MahaRERA registration and extension certificates

Regulatory cases

No MahaRERA deregistration, abeyance, NCLT, revocation or other order names these registrations.

Projects

Delay is measured against the RERA proposed completion date on the registration certificate; * still open: the date has passed and MahaRERA shows no completion yet.

ProjectLocalityStatusProposedRevisedDelay
Vidarbha Premier Nagri Phase 3 KalmeshwarP50500010477Kalmeshwar (Mcl)Completed31 Dec 201830 Oct 2020+22 mo
Balasaheb Deoras Sahaniwas Phase 2P50500011868Nagpur (M Corp.)Certificate Signed31 Mar 201830 Mar 2022+104 mo*
Vidarbhapremier Nagri YavatmalP51000011689Wadgaon (Ct)Completed31 Dec 201930 Dec 2021+24 mo
Vidarbha Premier Sahaniwas Jaitala.nagpurP50500011968Nagpur (M Corp.)Certificate Signed31 Jan 201830 Oct 2020+33 mo
The Vidarbha Premier Ambanagri Kiran Nagar AmravtiP50300013412Amravati (M Corp.)Completed31 Dec 2017—On date
The Vidarbha Premier Sahaniwas Chikhali Khurd NagpurP50500012223Nagpur (M Corp.)Certificate Signed31 Dec 201731 Dec 2019+24 mo

Prakash Narayanrao Raole, in questions

Does Prakash Narayanrao Raole finish projects on time?

Of 6 MahaRERA registrations whose promised completion date has arrived, 1 kept it (17%). The rest ran a median 24 mo late. Across Maharashtra, 73% kept their date.

How many projects has Prakash Narayanrao Raole registered with MahaRERA?

6 projects under 6 MahaRERA registrations; 5 completed on MahaRERA.

Does Prakash Narayanrao Raole have MahaRERA regulatory cases?

No MahaRERA deregistration, abeyance, NCLT, revocation or other order names its registrations.

SourcesMahaRERA project pages · registration and extension certificates · regulatory lists and ordersPersonal details of promoters are not shown.Report a problemMethodology