The Vidarbha Premier Ambanagri Kiran Nagar Amravti

Completed

Amravati (M Corp.), Amravati 444606 |Promoter: Prakash Narayanrao Raole

4 Oct 2017Registered with MahaRERA
31 Dec 2017Promised completion
20Buildings
73Units registered
0MahaRERA listings and ordersNone found

Project summary

As registered with MahaRERA and published on its project page

Project type
Others
Status on MahaRERA
Completed
Buildings
20
Unit types
2 BHK, B type, C type, D type, E type, F type, G type, H type, I type, J type, K type, A type shop, C type shop, D type hall, E type hall, 4 BHK, 3 BHK73 units in all
Land area for this project
7,500 sq m (80,729 sq ft)
Permissible built-up area
5,585 sq m (60,113 sq ft)
Sanctioned built-up area
5,585 sq m (60,113 sq ft)
Address
Khasra No 21, Near Old Bye Pass, KirannagarPIN 444606
Designated bank account
Maharashtra State Cooperative Bank
Litigation declared by promoter
None declared
Financial encumbrance declared
None declared

Location

Coordinates as published by MahaRERA

View on OpenStreetMap 20.89408, 77.76438
The Vidarbha Premier Ambanagri Kiran Nagar Amravti is at latitude 20.89408, longitude 77.76438.

Latest registered deals

No registered transactions matched to this project yetSales, resales and rentals appear here once registered documents from authorised IGR feeds are matched to this project.

Completion timeline

Registration date, the completion date promised at registration, and any extension since

Completion promised for 31 Dec 2017

The latest completion date on record passed 8 years and 10 months ago.

Registered
4 Oct 2017
Promised
31 Dec 2017

RERA registration

RegistrationRegisteredPromised completionRevised completionPromoterMahaRERA
P503000134124 Oct 201731 Dec 2017—Prakash Narayanrao RaoleProject page

20 buildings

Buildings and wings named in the registration

BuildingSanctioned floorsUnits
Block No 4546
Block No 539
Rh 121
Rh 1021
Rh 1121
Rh 1221
Rh 1321
Rh 1421
Rh 1521
Rh 1621
Rh 1721
Rh 1821
Rh 221
Rh 321
Rh 421
Rh 521
Rh 621
Rh 721
Rh 821
Rh 921

Source: registration certificate annexures and MahaRERA's project page. “Floors with CC” counts floors covered by a commencement certificate.

Units and parking

73 units registered

2 BHK · 2 unitsB type · 5 unitsC type · 2 unitsD type · 2 unitsE type · 2 unitsF type · 6 unitsG type · 6 unitsH type · 6 unitsI type · 6 unitsJ type · 6 unitsK type · 6 unitsA type shop · 3 unitsC type shop · 1 unitD type hall · 1 unitE type hall · 1 unit4 BHK · 6 units3 BHK · 12 units
BuildingTypeCarpet areaUnits
Block No 42 BHK140.59 sq m · 1,513 sq ft2
Block No 4B type148.94 sq m · 1,603 sq ft2
Block No 4C type148.73 sq m · 1,601 sq ft2
Block No 4D type140.06 sq m · 1,508 sq ft2
Block No 4E type140.92 sq m · 1,517 sq ft2
Block No 4F type417.27 sq m · 4,491 sq ft6
Block No 4G type442.05 sq m · 4,758 sq ft6
Block No 4H type441.44 sq m · 4,752 sq ft6
Block No 4I type412.86 sq m · 4,444 sq ft6
Block No 4J type415.38 sq m · 4,471 sq ft6
Block No 4K type416.22 sq m · 4,480 sq ft6
Block No 5A type shop70.94 sq m · 764 sq ft3
Block No 5B type68.34 sq m · 736 sq ft3
Block No 5C type shop33.45 sq m · 360 sq ft1
Block No 5D type hall171.21 sq m · 1,843 sq ft1
Block No 5E type hall83.9 sq m · 903 sq ft1
Rh 14 BHK106.08 sq m · 1,142 sq ft1
Rh 104 BHK115.31 sq m · 1,241 sq ft1
Rh 114 BHK107.52 sq m · 1,157 sq ft1
Rh 123 BHK105.56 sq m · 1,136 sq ft1
Rh 133 BHK105.56 sq m · 1,136 sq ft1
Rh 143 BHK105.56 sq m · 1,136 sq ft1
Rh 153 BHK105.56 sq m · 1,136 sq ft1
Rh 163 BHK105.56 sq m · 1,136 sq ft1
Rh 173 BHK105.56 sq m · 1,136 sq ft1
Rh 184 BHK116.21 sq m · 1,251 sq ft1
Rh 23 BHK106.08 sq m · 1,142 sq ft1
Rh 33 BHK99.79 sq m · 1,074 sq ft1
Rh 43 BHK99.79 sq m · 1,074 sq ft1
Rh 53 BHK99.79 sq m · 1,074 sq ft1
Rh 63 BHK99.79 sq m · 1,074 sq ft1
Rh 73 BHK99.79 sq m · 1,074 sq ft1
Rh 84 BHK101.6 sq m · 1,094 sq ft1
Rh 94 BHK115.31 sq m · 1,241 sq ft1

Parking

BuildingTypeTwo-wheelerFour-wheelerBusVisitorTotal
Block No 4Closed/Covered00001
Block No 4Open Space00000
Block No 5Closed/Covered00000
Block No 5Open Space00000
Rh 1Closed/Covered00000
Rh 1Open Space00000
Rh 10Closed/Covered00000
Rh 10Open Space00000
Rh 11Closed/Covered00000
Rh 11Open Space00000
Rh 12Closed/Covered00000
Rh 12Open Space00000
Rh 13Closed/Covered00000
Rh 13Open Space00000
Rh 14Closed/Covered00000
Rh 14Open Space00000
Rh 15Closed/Covered00000
Rh 15Open Space00000
Rh 16Closed/Covered00000
Rh 16Open Space00000
Rh 17Closed/Covered00000
Rh 17Open Space00000
Rh 18Closed/Covered00000
Rh 18Open Space00000
Rh 2Closed/Covered00000
Rh 2Open Space00000
Rh 3Closed/Covered00000
Rh 3Open Space00000
Rh 4Closed/Covered00000
Rh 4Open Space00000
Rh 5Closed/Covered00000
Rh 5Open Space00000
Rh 6Closed/Covered00000
Rh 6Open Space00000
Rh 7Closed/Covered00000
Rh 7Open Space00000
Rh 8Closed/Covered00000
Rh 8Open Space00000
Rh 9Closed/Covered00000
Rh 9Open Space00000

Source: MahaRERA project page, as the promoter filed it. Carpet areas are per unit.

Construction progress

Work completed, as the promoter reported it to MahaRERA (Form 1)

Block No 4

  • Excavation100%
  • Basement (if any)100%
  • Podiums (if any)0%
  • Plinth100%
  • Stilt Floor100%
  • Slabs of Super Structure100%
  • Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises100%
  • Sanitary Fittings within the flats / premises100%
  • Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks100%
  • External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.100%
  • Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.100%

Block No 5

  • Excavation100%
  • Basement (if any)100%
  • Podiums (if any)0%
  • Plinth100%
  • Stilt Floor0%
  • Slabs of Super Structure100%
  • Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises100%
  • Sanitary Fittings within the flats / premises100%
  • Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks100%
  • External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.100%
  • Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.100%

Rh 1

  • Excavation100%
  • Basement (if any)100%
  • Podiums (if any)0%
  • Plinth100%
  • Stilt Floor0%
  • Slabs of Super Structure100%
  • Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises100%
  • Sanitary Fittings within the flats / premises100%
  • Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks100%
  • External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.100%
  • Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.100%

Rh 10

  • Excavation100%
  • Basement (if any)100%
  • Podiums (if any)0%
  • Plinth100%
  • Stilt Floor0%
  • Slabs of Super Structure100%
  • Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises100%
  • Sanitary Fittings within the flats / premises100%
  • Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks100%
  • External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.100%
  • Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.100%

Rh 11

  • Excavation100%
  • Basement (if any)100%
  • Podiums (if any)0%
  • Plinth100%
  • Stilt Floor0%
  • Slabs of Super Structure100%
  • Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises100%
  • Sanitary Fittings within the flats / premises100%
  • Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks100%
  • External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.100%
  • Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.100%

Rh 12

  • Excavation100%
  • Basement (if any)100%
  • Podiums (if any)0%
  • Plinth100%
  • Stilt Floor0%
  • Slabs of Super Structure100%
  • Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises100%
  • Sanitary Fittings within the flats / premises100%
  • Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks100%
  • External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.100%
  • Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.100%

Rh 13

  • Excavation100%
  • Basement (if any)100%
  • Podiums (if any)0%
  • Plinth100%
  • Stilt Floor0%
  • Slabs of Super Structure100%
  • Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises100%
  • Sanitary Fittings within the flats / premises100%
  • Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks100%
  • External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.100%
  • Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.100%

Rh 14

  • Excavation100%
  • Basement (if any)100%
  • Podiums (if any)0%
  • Plinth100%
  • Stilt Floor0%
  • Slabs of Super Structure100%
  • Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises100%
  • Sanitary Fittings within the flats / premises100%
  • Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks100%
  • External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.100%
  • Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.100%

Rh 15

  • Excavation100%
  • Basement (if any)100%
  • Podiums (if any)0%
  • Plinth100%
  • Stilt Floor0%
  • Slabs of Super Structure100%
  • Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises100%
  • Sanitary Fittings within the flats / premises100%
  • Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks100%
  • External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.100%
  • Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.100%

Rh 16

  • Excavation100%
  • Basement (if any)100%
  • Podiums (if any)0%
  • Plinth100%
  • Stilt Floor0%
  • Slabs of Super Structure100%
  • Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises100%
  • Sanitary Fittings within the flats / premises100%
  • Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks100%
  • External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.100%
  • Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.100%

Rh 17

  • Excavation100%
  • Basement (if any)100%
  • Podiums (if any)0%
  • Plinth100%
  • Stilt Floor0%
  • Slabs of Super Structure100%
  • Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises100%
  • Sanitary Fittings within the flats / premises100%
  • Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks100%
  • External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.100%
  • Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.100%

Rh 18

  • Excavation100%
  • Basement (if any)100%
  • Podiums (if any)0%
  • Plinth100%
  • Stilt Floor0%
  • Slabs of Super Structure100%
  • Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises100%
  • Sanitary Fittings within the flats / premises100%
  • Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks100%
  • External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.100%
  • Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.100%

Rh 2

  • Excavation100%
  • Basement (if any)100%
  • Podiums (if any)0%
  • Plinth100%
  • Stilt Floor0%
  • Slabs of Super Structure100%
  • Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises100%
  • Sanitary Fittings within the flats / premises100%
  • Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks100%
  • External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.100%
  • Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.100%

Rh 3

  • Excavation100%
  • Basement (if any)100%
  • Podiums (if any)0%
  • Plinth100%
  • Stilt Floor0%
  • Slabs of Super Structure100%
  • Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises100%
  • Sanitary Fittings within the flats / premises100%
  • Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks100%
  • External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.100%
  • Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.100%

Rh 4

  • Excavation100%
  • Basement (if any)100%
  • Podiums (if any)0%
  • Plinth100%
  • Stilt Floor0%
  • Slabs of Super Structure100%
  • Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises100%
  • Sanitary Fittings within the flats / premises100%
  • Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks100%
  • External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.100%
  • Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.100%

Rh 5

  • Excavation100%
  • Basement (if any)100%
  • Podiums (if any)0%
  • Plinth100%
  • Stilt Floor0%
  • Slabs of Super Structure100%
  • Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises100%
  • Sanitary Fittings within the flats / premises100%
  • Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks100%
  • External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.100%
  • Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.100%

Rh 6

  • Excavation100%
  • Basement (if any)100%
  • Podiums (if any)0%
  • Plinth100%
  • Stilt Floor0%
  • Slabs of Super Structure100%
  • Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises100%
  • Sanitary Fittings within the flats / premises100%
  • Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks100%
  • External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.100%
  • Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.100%

Rh 7

  • Excavation100%
  • Basement (if any)100%
  • Podiums (if any)0%
  • Plinth100%
  • Stilt Floor0%
  • Slabs of Super Structure100%
  • Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises100%
  • Sanitary Fittings within the flats / premises100%
  • Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks100%
  • External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.100%
  • Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.100%

Rh 8

  • Excavation100%
  • Basement (if any)100%
  • Podiums (if any)0%
  • Plinth100%
  • Stilt Floor0%
  • Slabs of Super Structure100%
  • Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises100%
  • Sanitary Fittings within the flats / premises100%
  • Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks100%
  • External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.100%
  • Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.100%

Rh 9

  • Excavation100%
  • Basement (if any)100%
  • Podiums (if any)0%
  • Plinth100%
  • Stilt Floor0%
  • Slabs of Super Structure100%
  • Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises100%
  • Sanitary Fittings within the flats / premises100%
  • Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks100%
  • External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.100%
  • Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.100%

Common areas and amenities

  • Internal Roads & Footpaths100100%
  • Water Supply100100%
  • Sewerage (Chamber, Lines, Septic Tank , STP)100100%
  • Storm Water Drains100100%
  • Landscaping & Tree Planting100100%
  • Street Lighting100100%
  • Community BuildingsNot applicable
  • Treatment And Disposal Of Sewage And Sullage WaterNot applicable
  • Solid Waste Management And DisposalNot applicable
  • Water conservation /Rain water harvestingNot applicable
  • Energy managemcntNot applicable
  • Fire protection and fire safety requirementsNot applicable
  • Electrical meter room, sub-station, receiving stationNot applicable
  • Aggregate area of recreational Open SpaceNot applicable
  • Open ParkingNot applicable

Source: MahaRERA project page. Percentages are the promoter's own declaration, not an inspection.

Documents

41 documents held by Deedo, 60 filings listed on MahaRERA's project page

Title

Encumbrance

Form bs

Registration certificate

Commencement certificates

Form 2s

Form 4s

Form 5s

Others

Layout plans

Building plans

Allotment letter

Document library

  • Details of encumbrancesNot Applicable.pdf · uploaded 31 Jul 2017View
  • Declaration in FORM BWill be Submitted Later.pdf · uploaded 31 Jul 2017View
  • Certificates of Architect (Form 1)(Mandatory for only ongoing project)Will be Submitted Later.pdf · uploaded 31 Jul 2017View
  • Certificates of Engineer (Form 2)(Mandatory for only ongoing project)Will be Submitted Later.pdf · uploaded 31 Jul 2017View
  • Commencement Certificates / NA Order for plotted developmentWill be Submitted Later.pdf · uploaded 31 Jul 2017View
  • Copy of the legal title reportLEGAL.pdf · uploaded 31 Jul 2017View
  • Copy of Layout Approval (in case of layout)LAYOUT.pdf · uploaded 31 Jul 2017View
  • Proforma of Allotment letterALLOT.pdf · uploaded 31 Jul 2017View
  • Building Plan Approval (IOD)PALN.pdf · uploaded 31 Jul 2017View
  • Copy of Layout Approval (in case of layout)IMG_20170914_0024.pdf · uploaded 11 Oct 2017View
  • Declaration in FORM BIMG_20170914_0020.pdf · uploaded 11 Oct 2017View
  • Declaration in FORM BIMG_20170914_0021.pdf · uploaded 11 Oct 2017View
  • Declaration in FORM BIMG_20170914_0022.pdf · uploaded 11 Oct 2017View
  • Declaration in FORM BIMG_20170914_0023.pdf · uploaded 11 Oct 2017View
  • Certificates of Architect (Form 4)IMG_20170914_0001.pdf · uploaded 11 Oct 2017View
  • Certificates of Architect (Form 4)IMG_20170914_0002.pdf · uploaded 11 Oct 2017View
  • Certificates of Architect (Form 4)IMG_20170914_0003.pdf · uploaded 11 Oct 2017View
  • Certificates of Architect (Form 4)IMG_20170914_0004.pdf · uploaded 11 Oct 2017View
  • Certificates of Engineer (Form 2)(Mandatory for only ongoing project)IMG_20170914_0017.pdf · uploaded 11 Oct 2017View
  • Certificates of Engineer (Form 2)(Mandatory for only ongoing project)IMG_20170914_0018.pdf · uploaded 11 Oct 2017View
  • Certificates of Engineer (Form 2)(Mandatory for only ongoing project)IMG_20170914_0019.pdf · uploaded 11 Oct 2017View
  • Commencement Certificates / NA Order for plotted developmentIMG_20170914_0013.pdf · uploaded 11 Oct 2017View
  • Commencement Certificates / NA Order for plotted developmentIMG_20170914_0014.pdf · uploaded 11 Oct 2017View
  • Commencement Certificates / NA Order for plotted developmentIMG_20170914_0015.pdf · uploaded 11 Oct 2017View
  • Building Plan Approval (IOD)IMG_20170914_0005.pdf · uploaded 11 Oct 2017View
  • Building Plan Approval (IOD)IMG_20170914_0006.pdf · uploaded 11 Oct 2017View
  • Building Plan Approval (IOD)IMG_20170914_0007.pdf · uploaded 11 Oct 2017View
  • Building Plan Approval (IOD)IMG_20170914_0008.pdf · uploaded 11 Oct 2017View
  • Building Plan Approval (IOD)IMG_20170914_0009.pdf · uploaded 11 Oct 2017View
  • Building Plan Approval (IOD)IMG_20170914_0010.pdf · uploaded 11 Oct 2017View
  • Certificates of CA (Form 5)IMG_0001.pdf · uploaded 24 Oct 2017View
  • Certificates of CA (Form 5)IMG_0002.pdf · uploaded 24 Oct 2017View
  • OtherIMG_0008.pdf · uploaded 24 Oct 2017View
  • Certificates of CA (Form 5)IMG_0003.pdf · uploaded 24 Oct 2017View
  • Certificates of CA (Form 5)IMG_0004.pdf · uploaded 24 Oct 2017View
  • Certificates of CA (Form 5)IMG_0005.pdf · uploaded 24 Oct 2017View
  • Certificates of CA (Form 5)IMG_0006.pdf · uploaded 24 Oct 2017View
  • Certificates of CA (Form 5)IMG_0007.pdf · uploaded 24 Oct 2017View
  • Certificates of Architect (Form 4)IMG_0002.pdf · uploaded 30 Dec 2017View
  • OtherIMG_0001.pdf · uploaded 30 Dec 2017View
  • Occupancy Certificate/ Completion Certificate/ Architect's certificate of completion for plotted developmentIMG_0002.pdf · uploaded 27 Sep 2019View
  • Certificates of Architect (Form 4)IMG_0001.pdf · uploaded 27 Sep 2019View

Promoter documents

  • Declaration Form BWill be Submitted Later.pdf · uploaded 31 Jul 2017View
  • Legal Title reportLEGAL.pdf · uploaded 31 Jul 2017View
  • Declaration Form BIMG_20170914_0020.pdf · uploaded 11 Oct 2017View
  • Declaration Form BIMG_20170914_0021.pdf · uploaded 11 Oct 2017View
  • Declaration Form BIMG_20170914_0022.pdf · uploaded 11 Oct 2017View
  • Declaration Form BIMG_20170914_0023.pdf · uploaded 11 Oct 2017View

Technical documents

  • Layout ApprovalLAYOUT.pdfView
  • Building Plan ApprovalPALN.pdfView
  • Layout ApprovalIMG_20170914_0024.pdfView
  • Building Plan ApprovalIMG_20170914_0005.pdfView
  • Building Plan ApprovalIMG_20170914_0006.pdfView
  • Building Plan ApprovalIMG_20170914_0007.pdfView
  • Building Plan ApprovalIMG_20170914_0008.pdfView
  • Building Plan ApprovalIMG_20170914_0009.pdfView
  • Building Plan ApprovalIMG_20170914_0010.pdfView

Other legal documents

  • OtherIMG_0001.pdfView
  • OtherIMG_0008.pdfView

Proforma allotment letter

  • Proforma allotment letterALLOT.pdfView

Source: Certificates, orders and filings published by MahaRERA. Filings that can't be opened here are listed as they appear on MahaRERA's project page.

Regulatory record

Deedo hasn't found this project's RERA number in any MahaRERA list or order it has read: deregistered, abeyance, NCLT, quarterly-report non-compliance, revoked, regulatory and suo motu orders.

Source: MahaRERA regulatory lists and orders, checked against each RERA number.

Land

In Amravati (M Corp.), Amravati taluka

Survey, CTS, gat or plot numbers

KHASRA NO 21

As published on MahaRERA's project page

KHASRA NO 21

Boundaries

North
Kiran Nagar No 1
South
Govt Road
East
Kiran Nagar No 2
West
Part Land Of Same Trust

Source: registration certificates and MahaRERA's project page, as stated there.

Professionals

Architects, engineers, chartered accountants and agents named on the registration

RoleNameRegistration no.
ArchitectDhawad & Associates—
EngineerMs Sky Line—
OtherMs Shayona Corporation—
OtherVighnaharta Consulting Engineers—

Source: MahaRERA project page. Contact details are not shown.

Data through9 Oct 2026SourcesMahaRERA project search · registration certificates · MahaRERA project pageData through is when MahaRERA's project page was last read.Methodology