Poddar Housing And Development Limited
Deedo IDDD-GBX2Of 4 registrations whose promised date has arrived, 2 kept it (50%). The rest ran a median 47 mo late.
Delivery record
2 of 4 registrations with dates moved or missed their RERA date · months late against the original promise
4 registrations with dates · Source: MahaRERA registration and extension certificates
Regulatory cases
No MahaRERA deregistration, abeyance, NCLT, revocation or other order names these registrations.
Projects
Delay is measured against the RERA proposed completion date on the registration certificate; * still open: the date has passed and MahaRERA shows no completion yet.
| Project | Locality | Status | Proposed | Revised | Delay |
|---|---|---|---|---|---|
| Poddar Spraha Diamond Phase-IP51900002986 | Mumbai City | Certificate Signed | 31 Mar 2022 | 30 Sep 2022 | +56 mo* |
| Samruddhi Evergreen-Phase-4bP51700009016 | Badlapur (M Cl) | Completed | 31 Mar 2019 | — | On date |
| Samruddhi Evergreens-Phase-4aP51700009407 | Badlapur (M Cl) | Completed | 31 Mar 2018 | — | On date |
| Poddar Wondercity Phase - IP51700020032 | Badlapur (M Cl) | Certificate Signed | 30 Sep 2023 | 30 Sep 2023 | +38 mo* |
Poddar Housing And Development Limited, in questions
Does Poddar Housing And Development Limited finish projects on time?
Of 4 MahaRERA registrations whose promised completion date has arrived, 2 kept it (50%). The rest ran a median 47 mo late. Across Maharashtra, 73% kept their date.
How many projects has Poddar Housing And Development Limited registered with MahaRERA?
4 projects under 4 MahaRERA registrations; 2 completed on MahaRERA.
Does Poddar Housing And Development Limited have MahaRERA regulatory cases?
No MahaRERA deregistration, abeyance, NCLT, revocation or other order names its registrations.