Of 4 registrations whose promised date has arrived, 1 kept it (25%). The rest ran a median 35 mo late.

Projects44 RERA registrations
Kept RERA date25%Maharashtra: 73%
Median delay35 mowhen late
First sales on record0registered first-sale deeds matched so far
Regulatory cases0none on record

Delivery record

3 of 4 registrations with dates moved or missed their RERA date · months late against the original promise

4 registrations with dates · Source: MahaRERA registration and extension certificates

Regulatory cases

No MahaRERA deregistration, abeyance, NCLT, revocation or other order names these registrations.

Projects

Delay is measured against the RERA proposed completion date on the registration certificate; * still open: the date has passed and MahaRERA shows no completion yet.

ProjectLocalityStatusProposedRevisedDelay
Hiradeep ApartmentP49800018509Dhule (M Corp.)Lapsed30 Dec 2022—On date
Padmashree Residency IVP49800022439Dhule (M Corp.)Lapsed28 Aug 2023—+39 mo*
Padmashree Residency VP49800024259Dhule (M Corp.)Lapsed30 Dec 2023—+35 mo*
Padmashree Residency VIP49800024286Dhule (M Corp.)Lapsed30 Jan 2024—+34 mo*

Parag Subhash Ahire, in questions

Does Parag Subhash Ahire finish projects on time?

Of 4 MahaRERA registrations whose promised completion date has arrived, 1 kept it (25%). The rest ran a median 35 mo late. Across Maharashtra, 73% kept their date.

How many projects has Parag Subhash Ahire registered with MahaRERA?

4 projects under 4 MahaRERA registrations; 1 completed on MahaRERA.

Does Parag Subhash Ahire have MahaRERA regulatory cases?

No MahaRERA deregistration, abeyance, NCLT, revocation or other order names its registrations.

SourcesMahaRERA project pages · registration and extension certificates · regulatory lists and ordersPersonal details of promoters are not shown.Report a problemMethodology