NG Rathi Promoters
Deedo IDDD-RFT5Of 1 registration whose promised date has arrived, 0 kept it (0%). The rest ran a median 8 mo late.
Delivery record
2 of 2 registrations with dates moved or missed their RERA date · months late against the original promise
2 registrations with dates · Source: MahaRERA registration and extension certificates
Regulatory cases
No MahaRERA deregistration, abeyance, NCLT, revocation or other order names these registrations.
Projects
Delay is measured against the RERA proposed completion date on the registration certificate; * still open: the date has passed and MahaRERA shows no completion yet.
| Project | Locality | Status | Proposed | Revised | Delay |
|---|---|---|---|---|---|
| Vrundavan A WingP52100031233 | Pune (M Corp.) | Certificate Signed | 31 Dec 2025 | 31 Dec 2025 | +11 mo* |
| Serene SpacesPR1260002601339 | Wagholi | Certificate Signed | 31 Dec 2029 | 30 Apr 2030 | +4 mo |
NG Rathi Promoters, in questions
Does NG Rathi Promoters finish projects on time?
Of 1 MahaRERA registration whose promised completion date has arrived, 0 kept it (0%). The rest ran a median 8 mo late. Across Maharashtra, 73% kept their date.
How many projects has NG Rathi Promoters registered with MahaRERA?
2 projects under 2 MahaRERA registrations; 0 completed on MahaRERA.
Does NG Rathi Promoters have MahaRERA regulatory cases?
No MahaRERA deregistration, abeyance, NCLT, revocation or other order names its registrations.