Mont Vert Elegance

Company or firm · 4 projects · 4 MahaRERA registrations

4Projects4 RERA registrations
0Completedas reported on MahaRERA project pages
33%Kept RERA date1 of 3 past their proposed date, not extended
+20 moMedian delayvs RERA proposed date · 3 extended
1Regulatory casesMahaRERA orders and lists

Projects

Delay is measured against the RERA proposed completion date on the registration certificate.

ProjectLocalityRERA yearStatusProposedRevisedDelay
Mont Vert BelbrookP52100002449Bhugaon2017Certificate Signed31 Dec 201830 Jun 2022+42 months
Mont Vert BelairP52100002756Bhugaon2017Certificate Signed31 Dec 201830 Dec 2021+36 months
Mont Vert YoloP52100007210Bhugaon2017Certificate Signed30 Dec 202230 Dec 2022On date
Mont Vert BelcreekP52100029714Bhugaon2021Certificate Signed31 Dec 202830 Apr 2029+4 months

Delivery timeline

RERA proposed completion vs the latest revised date, per registration.

  • Mont Vert Belbrook+42 mo
  • Mont Vert Belair+36 mo
  • Mont Vert YoloOn date
  • Mont Vert Belcreek+4 mo

Track record notes

  • 1 of 3 registrations whose RERA proposed completion date has passed was never extended beyond it.
  • Longest extension on record: 42 months, for Mont Vert Belbrook (P52100002449).

Regulatory cases across projects

SourcesMahaRERA project pages · registration and extension certificates · regulatory lists and ordersPersonal details of promoters are not shown.Methodology