RegisteredRevised date passed1 extensionMahaRERA status: Certificate Signed

P52100002756

Mont Vert Belair · Bhugaon, Pune · Mont Vert Elegance

Promised for 31 Dec 2018, extended once to 30 Dec 2021 — and that date has passed without the project marked complete on MahaRERA.

7 years and 10 months past the original promise today.

What to watch

Facts from the record. A flag is a reason to ask questions, not a verdict.

  • Caution: Completion date extended from 31 Dec 2018 to 30 Dec 2021 (1 extension certificate on record).
  • Risk: The latest completion date on record, 30 Dec 2021, has passed.
  • Clear: Not on MahaRERA's deregistered, revoked, abeyance or insolvency lists.

Documents 2

Registration certificate4 Aug 2017View
Extension certificate9 Sep 2021View

Orders 0

No MahaRERA order or list names this number.

Questions about P52100002756

Is Mont Vert Belair delayed?

Yes. MahaRERA records a promised completion of 31 Dec 2018, revised to 30 Dec 2021, which has passed, and the project is not marked complete.

How many extensions has it had?

Deedo holds 1 extension certificate for P52100002756. The completion date moved from 31 Dec 2018 to 30 Dec 2021.

Who is the promoter?

MahaRERA records Mont Vert Elegance as the promoter of P52100002756.

Is it on any MahaRERA regulatory list?

No MahaRERA order or list that Deedo holds names P52100002756.

Answers are generated from the record.

Data through25 Oct 2026, 01:50SourcesMahaRERA project register · registration and extension certificates · regulatory lists and ordersMethodology