Mohan Hardasmal Tharwani
Deedo IDDD-19M1Of 11 registrations whose promised date has arrived, 7 kept it (64%). The rest ran a median 4 mo late.
Delivery record
9 of 19 registrations with dates moved or missed their RERA date · months late against the original promise
Show all 19 registrations
19 registrations with dates · Source: MahaRERA registration and extension certificates
Regulatory cases
No MahaRERA deregistration, abeyance, NCLT, revocation or other order names these registrations.
Projects
Delay is measured against the RERA proposed completion date on the registration certificate; * still open: the date has passed and MahaRERA shows no completion yet.
| Project | Locality | Status | Proposed | Revised | Delay |
|---|---|---|---|---|---|
| vedant imperial ABC phase 1P51700006197 | Badlapur (M Cl) | Certificate Signed | 30 Nov 2019 | 30 Nov 2019 | On date |
| Rituworld Phase III M and NP51700006857 | Badlapur | Certificate Signed | 30 Dec 2024 | 30 Dec 2024 | On date |
| vedant imperial bunglow 1 to 8 phase 2P51700007492 | Badlapur (M Cl) | Certificate Signed | 30 Dec 2024 | 30 Dec 2024 | On date |
| vedant imperial D phase 3P51700007549 | Badlapur (M Cl) | Certificate Signed | 30 Jun 2023 | 30 Jun 2023 | On date |
| vedant nakshatraP51700008414 | Badlapur | Certificate Signed | 30 Dec 2025 | 30 Dec 2025 | On date |
| vedantnakshatra L phase 3P51700008415 | Badlapur | Certificate Signed | 31 Aug 2027 | 31 Aug 2027 | On date |
| vedant nakshatra ABC phase 1P51700013039 | Badlapur (M Cl) | Certificate Signed | 31 Dec 2017 | 31 Dec 2017 | On date |
| Vedant Millenia HappinessP51700018689 | Titwala | Certificate Signed | 30 Nov 2021 | 28 Feb 2023 | +15 mo |
| Vedant Millenia HappinessP51700030699 | Titwala | Certificate Signed | 15 Dec 2025 | 15 Dec 2025 | On date |
| Vedant Nakshatra Wing J Phase VIP51700031084 | Badlapur | Certificate Signed | 31 Dec 2024 | 21 Feb 2025 | +2 mo |
| Vedant Millenia happinessP51700047571 | Titwala | Certificate Signed | 31 Dec 2029 | 31 Dec 2029 | On date |
| Vedant Empire Phase III Wing C-ClifftonP51700049801 | Gandhare | Certificate Signed | 30 Jun 2024 | 31 Mar 2025 | +9 mo |
| Vedant ConnectP51700049879 | Chikanghar | Certificate Signed | 31 Dec 2026 | 30 Apr 2027 | +4 mo |
| Vedant Empire Phase II Wing B-HamptonP51700049934 | Gandhare | Certificate Signed | 31 Dec 2027 | 30 Apr 2028 | +4 mo |
| Vedant Empire Phase I Wing A-EagletonP51700050201 | Gandhare | Certificate Signed | 31 Dec 2027 | 30 Apr 2028 | +4 mo |
| Vedant Millenia happinessP51700050205 | Titwala | Certificate Signed | 31 Dec 2027 | 30 Apr 2028 | +4 mo |
| vedant nakshatraP51700051733 | Badlapur | Certificate Signed | 30 Jun 2026 | 30 Oct 2026 | +5 mo* |
| Vedant Millenia happinessP51700055377 | Titwala | Certificate Signed | 31 Jul 2028 | 31 Jul 2028 | On date |
| Vedant Millenia Blue Moon Phase IVPM1330002502281 | Titwala | Certificate Signed | 30 Jun 2028 | 30 Oct 2028 | +4 mo |
Show all 19 registrationsShow fewer
Mohan Hardasmal Tharwani, in questions
Does Mohan Hardasmal Tharwani finish projects on time?
Of 11 MahaRERA registrations whose promised completion date has arrived, 7 kept it (64%). The rest ran a median 4 mo late. Across Maharashtra, 73% kept their date.
How many projects has Mohan Hardasmal Tharwani registered with MahaRERA?
15 projects under 19 MahaRERA registrations; 10 completed on MahaRERA.
Does Mohan Hardasmal Tharwani have MahaRERA regulatory cases?
No MahaRERA deregistration, abeyance, NCLT, revocation or other order names its registrations.