Laxmi Global

Company or firm · 3 projects · 3 MahaRERA registrations

Projects33 RERA registrations
Completed0as reported on MahaRERA project pages
Kept RERA date33%1 of 3 past their proposed date, not extended
Median delay+6 movs RERA proposed date · 2 extended
Regulatory cases0MahaRERA orders and lists

Projects

Delay is measured against the RERA proposed completion date on the registration certificate.

ProjectLocalityRERA yearStatusProposedRevisedDelay
Laxmi CastelloP52000001905Bopele2017Not reported31 Jan 2021—On date
Laxmi OrchidP52000008463Dhamote2017Not reported30 Jun 202130 Dec 2022+18 months
Laxmi Castello Phase-II, B1, A-Wing, B2, B-WingP52000028993Bopele2021Not reported31 Dec 202130 Jun 2022+6 months

Delivery timeline

RERA proposed completion vs the latest revised date, per registration.

  • Laxmi CastelloOn date
  • Laxmi Orchid+18 mo
  • Laxmi Castello Phase-II, B1, A-Wing, B2, B-Wing+6 mo

Track record notes

  • 1 of 3 registrations whose RERA proposed completion date has passed was never extended beyond it.
  • Longest extension on record: 18 months, for Laxmi Orchid (P52000008463).
  • No MahaRERA regulatory order or list names these registrations.

Regulatory cases across projects

None on recordNo MahaRERA deregistration, abeyance, NCLT, revocation or other order names these registrations.
SourcesMahaRERA project pages · registration and extension certificates · regulatory lists and ordersPersonal details of promoters are not shown.Methodology