RegisteredRevised date passed1 extensionMahaRERA status: Certificate Signed

P52000028993

Laxmi Castello Phase-II, B1, A-Wing, B2, B-Wing · Bopele, Raigarh · Laxmi Global

Promised for 31 Dec 2021, extended once to 30 Jun 2022 — and that date has passed without the project marked complete on MahaRERA.

4 years and 10 months past the original promise today.

What to watch

Facts from the record. A flag is a reason to ask questions, not a verdict.

  • Caution: Completion date extended from 31 Dec 2021 to 30 Jun 2022 (1 extension certificate on record).
  • Risk: The latest completion date on record, 30 Jun 2022, has passed.
  • Clear: Not on MahaRERA's deregistered, revoked, abeyance or insolvency lists.

Documents 2

Registration certificate23 Apr 2021View
Extension certificate2 Feb 2022View

Orders 0

No MahaRERA order or list names this number.

Questions about P52000028993

Is Laxmi Castello Phase-II, B1, A-Wing, B2, B-Wing delayed?

Yes. MahaRERA records a promised completion of 31 Dec 2021, revised to 30 Jun 2022, which has passed, and the project is not marked complete.

How many extensions has it had?

Deedo holds 1 extension certificate for P52000028993. The completion date moved from 31 Dec 2021 to 30 Jun 2022.

Who is the promoter?

MahaRERA records Laxmi Global as the promoter of P52000028993.

Is it on any MahaRERA regulatory list?

No MahaRERA order or list that Deedo holds names P52000028993.

Answers are generated from the record.

Data through25 Oct 2026, 02:53SourcesMahaRERA project register · registration and extension certificates · regulatory lists and ordersMethodology