Individual promoter · first RERA registration 2017

Jitendra Keshwani

Deedo IDDD-ZX0T

Of 1 registration whose promised date has arrived, 0 kept it (0%). The rest ran a median 107 mo late.

Projects11 RERA registration
Kept RERA date0%Maharashtra: 73%
Median delay107 mowhen late
First sales on record0registered first-sale deeds matched so far
Regulatory cases0none on record

Delivery record

1 of 1 registration with dates moved or missed their RERA date · months late against the original promise

1 registration with dates · Source: MahaRERA registration and extension certificates

Regulatory cases

No MahaRERA deregistration, abeyance, NCLT, revocation or other order names these registrations.

Projects

Delay is measured against the RERA proposed completion date on the registration certificate; * still open: the date has passed and MahaRERA shows no completion yet.

ProjectLocalityStatusProposedRevisedDelay
Adarsh ResidencyP50300004588Amravati (M Corp.)Lapsed31 Dec 2017—+107 mo*

Jitendra Keshwani, in questions

Does Jitendra Keshwani finish projects on time?

Of 1 MahaRERA registration whose promised completion date has arrived, 0 kept it (0%). The rest ran a median 107 mo late. Across Maharashtra, 73% kept their date.

How many projects has Jitendra Keshwani registered with MahaRERA?

1 project under 1 MahaRERA registration; 0 completed on MahaRERA.

Does Jitendra Keshwani have MahaRERA regulatory cases?

No MahaRERA deregistration, abeyance, NCLT, revocation or other order names its registrations.

SourcesMahaRERA project pages · registration and extension certificates · regulatory lists and ordersPersonal details of promoters are not shown.Report a problemMethodology