Jay Developers

Company or firm · 13 projects · 13 MahaRERA registrations

Also appears as JAYDEVELOPERS

Projects1313 RERA registrations
Completed0as reported on MahaRERA project pages
Kept RERA date75%9 of 12 past their proposed date, not extended
Median delay+0 movs RERA proposed date · 3 extended
Regulatory cases0MahaRERA orders and lists

Projects

Delay is measured against the RERA proposed completion date on the registration certificate.

ProjectLocalityRERA yearStatusProposedRevisedDelay
VijayparadiseparkP51600004967Nashik (M Corp.)2017Not reported31 Dec 2018—On date
Vijay GalaxyP51600006062Nashik (M Corp.)2017Not reported31 Dec 2018—On date
SaivijaytradecenterP51600006432Nashik (M Corp.)2017Not reported31 Dec 2019—On date
Vijay ResidencyP51600007898Aanandwali2017Not reported31 Dec 2018—On date
SaishrushtiP51600008058Nashik (M Corp.)2017Not reported31 Oct 2027—On date
SaivijayiconP51600009951Nashik (M Corp.)2017Not reported31 Dec 2019—On date
SamrudhipalaceP51600010696Nashik (M Corp.)2017Not reported31 Dec 2018—On date
Sai EmpireP51600011132Nashik (M Corp.)2017Not reported31 Dec 2020—On date
Vijay SonnetP51600011372Nashik (M Corp.)2017Not reported31 Dec 2018—On date
VijayshrushtiP51600011620Nashik (M Corp.)2017Not reported31 Dec 201830 Jun 2023+54 months
Vijay RoyalP51600011816Nashik (M Corp.)2017Not reported31 Dec 2018—On date
Vijay AnnexP51600012034Nashik (M Corp.)2017Not reported31 Dec 201830 Jun 2024+66 months
Sai AshaP51600031914Nashik2021Not reported4 Mar 202430 Dec 2025+21 months

Delivery timeline

RERA proposed completion vs the latest revised date, per registration.

  • VijayparadiseparkOn date
  • Vijay GalaxyOn date
  • SaivijaytradecenterOn date
  • Vijay ResidencyOn date
  • SaishrushtiOn date
  • SaivijayiconOn date
  • SamrudhipalaceOn date
  • Sai EmpireOn date
  • Vijay SonnetOn date
  • Vijayshrushti+54 mo
  • Vijay RoyalOn date
  • Vijay Annex+66 mo
  • Sai Asha+21 mo

Track record notes

  • 9 of 12 registrations whose RERA proposed completion date has passed were never extended beyond it.
  • Longest extension on record: 66 months, for Vijay Annex (P51600012034).
  • No MahaRERA regulatory order or list names these registrations.
  • MahaRERA records spell this promoter's name 2 ways; all of them are linked to this page through its registrations.

Regulatory cases across projects

None on recordNo MahaRERA deregistration, abeyance, NCLT, revocation or other order names these registrations.
SourcesMahaRERA project pages · registration and extension certificates · regulatory lists and ordersPersonal details of promoters are not shown.Methodology