Projects: P + 11 digits (or two letters + 13 digits, like PR1260002500851). Agents: A + 11 digits.

Completed

P51600011132

Sai Empire · Nashik (M Corp.), Nashik · Jay Developers

Promised for 31 Dec 2020; MahaRERA reports the project completed.

What to watch

Facts from the record. A flag is a reason to ask questions, not a verdict.

  • Clear: MahaRERA reports the project as completed.
  • Clear: Not on MahaRERA's deregistered, revoked, abeyance or insolvency lists.

Documents 26

Commencement certificate30 Jul 2017View
Form B30 Jul 2017View
Title report31 Jul 2017View
Encumbrance details31 Jul 2017View
Form 131 Jul 2017View
Form 131 Oct 2017View
Form 231 Oct 2017View
Commencement certificate10 Apr 2018View
Show all 26 documents
Form 210 Apr 2018View
Form 57 Jan 2020View
Form 2A5 Feb 2020View
Registration certificate18 May 2020View
Other22 Jun 2021View
OtherView
OtherView
OtherView
Layout planView
Building planView
Building planView
Building planView
OtherView
Allotment letterView
OtherView
OtherView
OtherView
OtherView

Orders 0

No MahaRERA order or list names this number.

Questions about P51600011132

Is Sai Empire delayed?

MahaRERA reports it completed. Its promised completion date was 31 Dec 2020.

How many extensions has it had?

Deedo holds 0 extension certificates for P51600011132.

Who is the promoter?

MahaRERA records Jay Developers as the promoter of P51600011132.

Is it on any MahaRERA regulatory list?

No MahaRERA order or list that Deedo holds names P51600011132.

Answers are generated from the record.

Data through4 Nov 2026, 03:20SourcesMahaRERA project register · registration and extension certificates · regulatory lists and ordersReport a problemMethodology