Jashnani Construction Private Limited

Deedo IDDD-ECG5

Of 9 registrations whose promised date has arrived, 8 kept it (89%). The rest ran a median 12 mo late — longer than Maharashtra's 4 mo.

Projects89 RERA registrations
Kept RERA date89%Maharashtra: 73%
Median delay12 mowhen late · Maharashtra: 4 mo
First sales on record0registered first-sale deeds matched so far
Regulatory cases0none on record

Delivery record

1 of 9 registrations with dates moved or missed their RERA date · months late against the original promise

9 registrations with dates · Source: MahaRERA registration and extension certificates

Regulatory cases

No MahaRERA deregistration, abeyance, NCLT, revocation or other order names these registrations.

Projects

Delay is measured against the RERA proposed completion date on the registration certificate; * still open: the date has passed and MahaRERA shows no completion yet.

ProjectLocalityStatusProposedRevisedDelay
Chintamani Habitat DaffodilsP51700001557ShahapurCertificate Signed31 Dec 201731 Dec 2017On date
Chintamani Habitat Daffodils Type A1 - DP51700001558Shahapur (Ct)Certificate Signed30 Dec 202330 Dec 2023On date
Chintamani Habitat DaffodilsP51700001853ShahapurCertificate Signed30 Sep 202030 Sep 2020On date
Chintamani Heights Type E Wing Q R SP51700004624CherpoliCertificate Signed31 Mar 201931 Mar 2019On date
Chintamani Habitat Lotus Type C - JP51700005632Shahapur (Ct)Certificate Signed30 Mar 202430 Mar 2024On date
Chintamani Habitat Angelica Type K And LP51700017614Shahapur (Ct)Certificate Signed30 Dec 202430 Dec 2024On date
Chintamani PlazaP51700019597Gotheghar (Ct)Certificate Signed30 Dec 202430 Dec 2024On date
Chintamani MeadowsP51700024889Shahapur (Ct)Certificate Signed30 Dec 202530 Dec 2026+12 mo
Chintamani Habitat Jasmine Type A-B-JP51700034891Shahapur (Ct)Certificate Signed31 Dec 202531 Dec 2025On date

Jashnani Construction Private Limited, in questions

Does Jashnani Construction Private Limited finish projects on time?

Of 9 MahaRERA registrations whose promised completion date has arrived, 8 kept it (89%). The rest ran a median 12 mo late. Across Maharashtra, 73% kept their date.

How many projects has Jashnani Construction Private Limited registered with MahaRERA?

8 projects under 9 MahaRERA registrations; 8 completed on MahaRERA.

Does Jashnani Construction Private Limited have MahaRERA regulatory cases?

No MahaRERA deregistration, abeyance, NCLT, revocation or other order names its registrations.

SourcesMahaRERA project pages · registration and extension certificates · regulatory lists and ordersPersonal details of promoters are not shown.Report a problemMethodology