Jashnani Construction Private Limited
Deedo IDDD-ECG5Of 9 registrations whose promised date has arrived, 8 kept it (89%). The rest ran a median 12 mo late — longer than Maharashtra's 4 mo.
Delivery record
1 of 9 registrations with dates moved or missed their RERA date · months late against the original promise
9 registrations with dates · Source: MahaRERA registration and extension certificates
Regulatory cases
No MahaRERA deregistration, abeyance, NCLT, revocation or other order names these registrations.
Projects
Delay is measured against the RERA proposed completion date on the registration certificate; * still open: the date has passed and MahaRERA shows no completion yet.
| Project | Locality | Status | Proposed | Revised | Delay |
|---|---|---|---|---|---|
| Chintamani Habitat DaffodilsP51700001557 | Shahapur | Certificate Signed | 31 Dec 2017 | 31 Dec 2017 | On date |
| Chintamani Habitat Daffodils Type A1 - DP51700001558 | Shahapur (Ct) | Certificate Signed | 30 Dec 2023 | 30 Dec 2023 | On date |
| Chintamani Habitat DaffodilsP51700001853 | Shahapur | Certificate Signed | 30 Sep 2020 | 30 Sep 2020 | On date |
| Chintamani Heights Type E Wing Q R SP51700004624 | Cherpoli | Certificate Signed | 31 Mar 2019 | 31 Mar 2019 | On date |
| Chintamani Habitat Lotus Type C - JP51700005632 | Shahapur (Ct) | Certificate Signed | 30 Mar 2024 | 30 Mar 2024 | On date |
| Chintamani Habitat Angelica Type K And LP51700017614 | Shahapur (Ct) | Certificate Signed | 30 Dec 2024 | 30 Dec 2024 | On date |
| Chintamani PlazaP51700019597 | Gotheghar (Ct) | Certificate Signed | 30 Dec 2024 | 30 Dec 2024 | On date |
| Chintamani MeadowsP51700024889 | Shahapur (Ct) | Certificate Signed | 30 Dec 2025 | 30 Dec 2026 | +12 mo |
| Chintamani Habitat Jasmine Type A-B-JP51700034891 | Shahapur (Ct) | Certificate Signed | 31 Dec 2025 | 31 Dec 2025 | On date |
Jashnani Construction Private Limited, in questions
Does Jashnani Construction Private Limited finish projects on time?
Of 9 MahaRERA registrations whose promised completion date has arrived, 8 kept it (89%). The rest ran a median 12 mo late. Across Maharashtra, 73% kept their date.
How many projects has Jashnani Construction Private Limited registered with MahaRERA?
8 projects under 9 MahaRERA registrations; 8 completed on MahaRERA.
Does Jashnani Construction Private Limited have MahaRERA regulatory cases?
No MahaRERA deregistration, abeyance, NCLT, revocation or other order names its registrations.