Chintamani Meadows
Certificate SignedShahapur (Ct), Thane 421601 |Promoter: Jashnani Construction Private Limited
Project summary
As registered with MahaRERA and published on its project page
- Project type
- Others
- Status on MahaRERA
- Certificate Signed
- Buildings
- 4
- Unit types
- 1BHK, 2BHK, Shop, Flats, Flat238 units in all
- Address
- S.no.6/2a, 6/2b, Behind Chintamani Residency, ShahapurPIN 421601
- Designated bank account
- 154
- Developed in phases
- Yes
Location
Coordinates as published by MahaRERA
Registered transactions
Completion timeline
Registration date, the completion date promised at registration, and any extension since
Completion pushed back 1 year
- Registered
- 9 Mar 2020
- Promised
- 30 Dec 2025
- Revised
- 30 Dec 2026
RERA registration
| Registration | Registered | Promised completion | Revised completion | Promoter | MahaRERA |
|---|---|---|---|---|---|
| P51700024889 | 9 Mar 2020 | 30 Dec 2025 | 30 Dec 2026 | Jashnani Construction Private Limited | Project page |
4 buildings
Buildings and wings named in the registration
| Building | Sanctioned floors | Units |
|---|---|---|
| Chintamani Meadows Building No 3 Wings A B C | 5 | 69 |
| Chintamani Meadows Building No 4 Wings A B C | 5 | 74 |
| Chintamani Meadows Building No 5 Wings A B | 5 | 67 |
| Chintamani Meadows Building No 7 | 5 | 28 |
Source: registration certificate annexures and MahaRERA's project page. “Floors with CC” counts floors covered by a commencement certificate.
Units and parking
13 of 238 units booked (5%), as the promoter reported to MahaRERA
| Building | Type | Carpet area | Units | Booked |
|---|---|---|---|---|
| Chintamani Meadows Building No 3 Wings A B C | 1BHK | 30.27 sq m · 326 sq ft | 4 | 0 |
| Chintamani Meadows Building No 3 Wings A B C | 1BHK | 31 sq m · 334 sq ft | 4 | 0 |
| Chintamani Meadows Building No 3 Wings A B C | 1BHK | 32.33 sq m · 348 sq ft | 8 | 0 |
| Chintamani Meadows Building No 3 Wings A B C | 1BHK | 32.5 sq m · 350 sq ft | 8 | 0 |
| Chintamani Meadows Building No 3 Wings A B C | 1BHK | 32.55 sq m · 350 sq ft | 4 | 0 |
| Chintamani Meadows Building No 3 Wings A B C | 1BHK | 33.02 sq m · 355 sq ft | 4 | 0 |
| Chintamani Meadows Building No 3 Wings A B C | 1BHK | 33.4 sq m · 360 sq ft | 4 | 0 |
| Chintamani Meadows Building No 3 Wings A B C | 1BHK | 33.85 sq m · 364 sq ft | 4 | 0 |
Show all 55 unit rowsShow fewer unit rows
| Building | Type | Carpet area | Units | Booked |
|---|---|---|---|---|
| Chintamani Meadows Building No 3 Wings A B C | 1BHK | 34.1 sq m · 367 sq ft | 8 | 0 |
| Chintamani Meadows Building No 3 Wings A B C | 1BHK | 34.4 sq m · 370 sq ft | 4 | 0 |
| Chintamani Meadows Building No 3 Wings A B C | 2BHK | 41.75 sq m · 449 sq ft | 4 | 0 |
| Chintamani Meadows Building No 3 Wings A B C | Shop | 7.6 sq m · 82 sq ft | 2 | 0 |
| Chintamani Meadows Building No 3 Wings A B C | Shop | 8.1 sq m · 87 sq ft | 2 | 0 |
| Chintamani Meadows Building No 3 Wings A B C | Shop | 9.8 sq m · 105 sq ft | 2 | 0 |
| Chintamani Meadows Building No 3 Wings A B C | Shop | 9.95 sq m · 107 sq ft | 7 | 0 |
| Chintamani Meadows Building No 4 Wings A B C | 1BHK | 31.48 sq m · 339 sq ft | 1 | 0 |
| Chintamani Meadows Building No 4 Wings A B C | 1BHK | 32.19 sq m · 346 sq ft | 1 | 0 |
| Chintamani Meadows Building No 4 Wings A B C | 1BHK | 32.33 sq m · 348 sq ft | 1 | 0 |
| Chintamani Meadows Building No 4 Wings A B C | 1BHK | 32.6 sq m · 351 sq ft | 4 | 0 |
| Chintamani Meadows Building No 4 Wings A B C | 1BHK | 32.61 sq m · 351 sq ft | 4 | 0 |
| Chintamani Meadows Building No 4 Wings A B C | 1BHK | 33.13 sq m · 357 sq ft | 4 | 0 |
| Chintamani Meadows Building No 4 Wings A B C | 1BHK | 33.23 sq m · 358 sq ft | 4 | 0 |
| Chintamani Meadows Building No 4 Wings A B C | 1BHK | 33.28 sq m · 358 sq ft | 16 | 0 |
| Chintamani Meadows Building No 4 Wings A B C | 1BHK | 33.73 sq m · 363 sq ft | 8 | 0 |
| Chintamani Meadows Building No 4 Wings A B C | 1BHK | 33.88 sq m · 365 sq ft | 4 | 0 |
| Chintamani Meadows Building No 4 Wings A B C | 1BHK | 35.02 sq m · 377 sq ft | 4 | 0 |
| Chintamani Meadows Building No 4 Wings A B C | 2BHK | 45.32 sq m · 488 sq ft | 4 | 0 |
| Chintamani Meadows Building No 4 Wings A B C | 2BHK | 45.65 sq m · 491 sq ft | 4 | 0 |
| Chintamani Meadows Building No 4 Wings A B C | Shop | 6.9 sq m · 74 sq ft | 1 | 0 |
| Chintamani Meadows Building No 4 Wings A B C | Shop | 8.1 sq m · 87 sq ft | 1 | 0 |
| Chintamani Meadows Building No 4 Wings A B C | Shop | 8.75 sq m · 94 sq ft | 1 | 0 |
| Chintamani Meadows Building No 4 Wings A B C | Shop | 8.85 sq m · 95 sq ft | 2 | 0 |
| Chintamani Meadows Building No 4 Wings A B C | Shop | 9.4 sq m · 101 sq ft | 1 | 0 |
| Chintamani Meadows Building No 4 Wings A B C | Shop | 9.42 sq m · 101 sq ft | 1 | 0 |
| Chintamani Meadows Building No 4 Wings A B C | Shop | 9.55 sq m · 103 sq ft | 1 | 0 |
| Chintamani Meadows Building No 4 Wings A B C | Shop | 9.7 sq m · 104 sq ft | 2 | 0 |
| Chintamani Meadows Building No 4 Wings A B C | Shop | 9.8 sq m · 105 sq ft | 4 | 0 |
| Chintamani Meadows Building No 4 Wings A B C | Shop | 12.05 sq m · 130 sq ft | 1 | 0 |
| Chintamani Meadows Building No 5 Wings A B | Flats | 41.35 sq m · 445 sq ft | 7 | 2 |
| Chintamani Meadows Building No 5 Wings A B | Flats | 42.96 sq m · 462 sq ft | 7 | 4 |
| Chintamani Meadows Building No 5 Wings A B | Flats | 46.67 sq m · 502 sq ft | 7 | 0 |
| Chintamani Meadows Building No 5 Wings A B | Flats | 48.75 sq m · 525 sq ft | 7 | 1 |
| Chintamani Meadows Building No 5 Wings A B | Flats | 50.3 sq m · 541 sq ft | 7 | 0 |
| Chintamani Meadows Building No 5 Wings A B | Flats | 51.43 sq m · 554 sq ft | 7 | 0 |
| Chintamani Meadows Building No 5 Wings A B | Flats | 52.09 sq m · 561 sq ft | 7 | 1 |
| Chintamani Meadows Building No 5 Wings A B | Flats | 56.68 sq m · 610 sq ft | 7 | 1 |
| Chintamani Meadows Building No 5 Wings A B | Shop | 11.89 sq m · 128 sq ft | 2 | 0 |
| Chintamani Meadows Building No 5 Wings A B | Shop | 15.22 sq m · 164 sq ft | 5 | 0 |
| Chintamani Meadows Building No 5 Wings A B | Shop | 15.5 sq m · 167 sq ft | 1 | 0 |
| Chintamani Meadows Building No 5 Wings A B | Shop | 19.66 sq m · 212 sq ft | 1 | 0 |
| Chintamani Meadows Building No 5 Wings A B | Shop | 22.43 sq m · 241 sq ft | 1 | 0 |
| Chintamani Meadows Building No 5 Wings A B | Shop | 29.5 sq m · 318 sq ft | 1 | 0 |
| Chintamani Meadows Building No 7 | Flat | 44.86 sq m · 483 sq ft | 7 | 1 |
| Chintamani Meadows Building No 7 | Flat | 54.12 sq m · 583 sq ft | 7 | 0 |
| Chintamani Meadows Building No 7 | Flat | 60.48 sq m · 651 sq ft | 14 | 3 |
Source: MahaRERA project page, as the promoter filed it. Carpet areas are per unit.
Documents
2 documents held by Deedo, 291 filings listed on MahaRERA's project page
Finance
- PAN CardPAN.pdf · uploaded 25 Feb 2020Source
Legal
- Legal Title reportTitle certificate.pdf · uploaded 25 Feb 2020Source
- Declaration Form BShiv sir Declaration.pdf · uploaded 25 Feb 2020Source
- Declaration Form BLandlord Declaration 1.pdf · uploaded 25 Feb 2020Source
- Declaration Form BLandlord Declaration.pdf · uploaded 25 Feb 2020Source
- Declaration Form Bnotary shiv sir.pdf · uploaded 17 Jun 2023Source
Show all 293 documentsShow fewer documents
Migrated
- 1 PAN CardPAN.pdf · uploaded 25 Feb 2020Source
- 1 Copy of the legal title reportTitle certificate.pdf · uploaded 25 Feb 2020Source
- 1 Details of encumbrancesencumbrances.pdf · uploaded 25 Feb 2020Source
- 1 Copy of Layout Approval (in case of layout)Layout.pdf · uploaded 25 Feb 2020Source
- 1 Building Plan Approval / NA Order for plotted developmentbldg 3.pdf · uploaded 25 Feb 2020Source
- 2 Building Plan Approval / NA Order for plotted developmentbldg 4-compressed.pdf · uploaded 25 Feb 2020Source
- 3 Building Plan Approval / NA Order for plotted developmentbldg 5.pdf · uploaded 25 Feb 2020Source
- 4 Building Plan Approval / NA Order for plotted developmentBldg 7.pdf · uploaded 25 Feb 2020Source
- 1 Commencement Certificates / NA Order for plotted developmentCHINTAMANI MEADOWS NA ORDER 1.pdf · uploaded 25 Feb 2020Source
- 2 Commencement Certificates / NA Order for plotted developmentCHINTAMANI MEADOWS NA ORDER 2.pdf · uploaded 25 Feb 2020Source
- 3 Commencement Certificates / NA Order for plotted developmentCC.pdf · uploaded 25 Feb 2020Source
- 1 Declaration in FORM BShiv sir Declaration.pdf · uploaded 25 Feb 2020Source
- 2 Declaration in FORM BLandlord Declaration 1.pdf · uploaded 25 Feb 2020Source
- 3 Declaration in FORM BLandlord Declaration.pdf · uploaded 25 Feb 2020Source
- 1 Architect’s Certificate of Percentage of Completion of Work (Form 1)Architect Certificate.pdf · uploaded 25 Feb 2020Source
- 1 Engineer’s Certificate on Cost Incurred on Project (Form 2)Engineer Certificate.pdf · uploaded 25 Feb 2020Source
- 1 CA Certificate on Project Cost & Fund withdrawal (Form 3)Form 3.pdf · uploaded 25 Feb 2020Source
- 1 Proforma of Allotment letterDraft Agreement.pdf · uploaded 25 Feb 2020Source
- 2 Proforma of Allotment letterMEADOWS ALLOTMENT LETTER.pdf · uploaded 6 Mar 2020Source
- 1 Engineers Certificate on Quality Assurance (Form 2A FY 2020-21)FORM 2A CM-3 WING A-B-C-2021.pdf · uploaded 7 Jul 2021Source
- 2 Architect’s Certificate of Percentage of Completion of Work (Form 1)CHINTAMANI MEADOWS FORM-1.pdf · uploaded 14 Aug 2021Source
- 2 Engineer’s Certificate on Cost Incurred on Project (Form 2)CHINTAMANI MEADOWS FORM -2.pdf · uploaded 14 Aug 2021Source
- 2 Engineers Certificate on Quality Assurance (Form 2A FY 2020-21)CHINTAMANI MEADOWS FORM-2A.pdf · uploaded 14 Aug 2021Source
- 1 Disclosure of sold/ booked inventoryCHINTAMANI MEADOWS INVENTORY.pdf · uploaded 14 Aug 2021Source
- 2 CA Certificate on Project Cost & Fund withdrawal (Form 3)chintamani meadows form 3.pdf · uploaded 14 Aug 2021Source
- 3 Architect’s Certificate of Percentage of Completion of Work (Form 1)MEADOWS FORM 1.pdf · uploaded 5 Oct 2021Source
- 3 Engineer’s Certificate on Cost Incurred on Project (Form 2)MEADOWS FORM 2.pdf · uploaded 5 Oct 2021Source
- 3 Engineers Certificate on Quality Assurance (Form 2A FY 2020-21)MEADOWS FORM 2A.pdf · uploaded 5 Oct 2021Source
- 2 Disclosure of sold/ booked inventoryMEADOWS INVENTORY 30-09-2021_20211005_125756.pdf · uploaded 5 Oct 2021Source
- 3 CA Certificate on Project Cost & Fund withdrawal (Form 3)MEADOWS FORM 3.pdf · uploaded 5 Oct 2021Source
- 4 Architect’s Certificate of Percentage of Completion of Work (Form 1)FORM 1 MEADOWS.pdf · uploaded 5 Jan 2022Source
- 4 Engineer’s Certificate on Cost Incurred on Project (Form 2)FORM 2 MEADOWS.pdf · uploaded 5 Jan 2022Source
- 4 Engineers Certificate on Quality Assurance (Form 2A FY 2020-21)FORM 2A MEADOWS.pdf · uploaded 5 Jan 2022Source
- 3 Disclosure of sold/ booked inventoryINVENTORY MEADOWS.pdf · uploaded 5 Jan 2022Source
- 4 CA Certificate on Project Cost & Fund withdrawal (Form 3)FORM 3 MEADOWS.pdf · uploaded 5 Jan 2022Source
- 5 Architect’s Certificate of Percentage of Completion of Work (Form 1)FORM 1 ANGELICA.pdf · uploaded 7 Apr 2022Source
- 6 Architect’s Certificate of Percentage of Completion of Work (Form 1)FORM 1 MEADOWS.pdf · uploaded 7 Apr 2022Source
- 7 Architect’s Certificate of Percentage of Completion of Work (Form 1)UNDER TAKING MEADOWS.pdf · uploaded 7 Apr 2022Source
- 8 Architect’s Certificate of Percentage of Completion of Work (Form 1)FORM 1 MEADOWS.pdf · uploaded 7 Apr 2022Source
- 5 Engineer’s Certificate on Cost Incurred on Project (Form 2)FORM 2 MEADOWS.pdf · uploaded 7 Apr 2022Source
- 6 Engineer’s Certificate on Cost Incurred on Project (Form 2)UNDER TAKING MEADOWS.pdf · uploaded 7 Apr 2022Source
- 7 Engineer’s Certificate on Cost Incurred on Project (Form 2)FORM 2 MEADOWS.pdf · uploaded 7 Apr 2022Source
- 5 Engineers Certificate on Quality Assurance (Form 2A FY 2020-21)FORM 2A MEADOWS BLDG 03.pdf · uploaded 7 Apr 2022Source
- 6 Engineers Certificate on Quality Assurance (Form 2A FY 2020-21)FORM 2A MEADOWS BLDG 04.pdf · uploaded 7 Apr 2022Source
- 4 Disclosure of sold/ booked inventory31-03-2022 INVENTORY MEADOWS.pdf · uploaded 7 Apr 2022Source
- 5 CA Certificate on Project Cost & Fund withdrawal (Form 3)FORM 3 MEADOWSS.pdf · uploaded 7 Apr 2022Source
- 1 Annual Audit Report of Statutory CA (Form 5) (FY 2020-21)CHINTAMANI MEADOWS .pdf · uploaded 15 Apr 2022Source
- 9 Architect’s Certificate of Percentage of Completion of Work (Form 1)FORM 1 MEADOWS_compressed (1).pdf · uploaded 6 Jul 2022Source
- 8 Engineer’s Certificate on Cost Incurred on Project (Form 2)FORM 2 MEADOWS_compressed.pdf · uploaded 6 Jul 2022Source
- 7 Engineers Certificate on Quality Assurance (Form 2A FY 2020-21)FORM 2A MEADOWS BUILDING 3.pdf · uploaded 6 Jul 2022Source
- 8 Engineers Certificate on Quality Assurance (Form 2A FY 2020-21)FORM 2A MEADOWS BUILDING 4.pdf · uploaded 6 Jul 2022Source
- 5 Disclosure of sold/ booked inventoryINVENTORY MEADOWS BUILDING 3 - 4_compressed.pdf · uploaded 6 Jul 2022Source
- 6 CA Certificate on Project Cost & Fund withdrawal (Form 3)FORM 3 MEADOWS_compressed (2).pdf · uploaded 6 Jul 2022Source
- 10 Architect’s Certificate of Percentage of Completion of Work (Form 1)CM FORM 1.pdf · uploaded 6 Oct 2022Source
- 9 Engineer’s Certificate on Cost Incurred on Project (Form 2)CM FORM 2.pdf · uploaded 6 Oct 2022Source
- 9 Engineers Certificate on Quality Assurance (Form 2A FY 2020-21)CM 3 FORM 2A.pdf · uploaded 6 Oct 2022Source
- 10 Engineers Certificate on Quality Assurance (Form 2A FY 2020-21)CM 4 FORM 2A.pdf · uploaded 6 Oct 2022Source
- 6 Disclosure of sold/ booked inventoryCM INVENTORY.pdf · uploaded 6 Oct 2022Source
- 7 CA Certificate on Project Cost & Fund withdrawal (Form 3)CM FORM 3.pdf · uploaded 6 Oct 2022Source
- 1 Annual Audit Report of Statutory CA (Form 5) (FY 2021-22)CHINTAMANI MEADOW.pdf · uploaded 29 Oct 2022Source
- 11 Architect’s Certificate of Percentage of Completion of Work (Form 1)FORM 1 MEADOWS.pdf · uploaded 7 Jan 2023Source
- 10 Engineer’s Certificate on Cost Incurred on Project (Form 2)FORM 2 MEADOWS.pdf · uploaded 7 Jan 2023Source
- 1 Engineers Certificate on Quality Assurance (Form 2A FY 2021-22)FORM 2A MEADOWS BLDG 03.pdf · uploaded 7 Jan 2023Source
- 2 Engineers Certificate on Quality Assurance (Form 2A FY 2021-22)FORM 2A MEADOWS BLDG 04.pdf · uploaded 7 Jan 2023Source
- 7 Disclosure of sold/ booked inventoryMEADOWS INVENTORY.pdf · uploaded 7 Jan 2023Source
- 8 CA Certificate on Project Cost & Fund withdrawal (Form 3)FORM 3 MEADOWS.pdf · uploaded 7 Jan 2023Source
- 12 Architect’s Certificate of Percentage of Completion of Work (Form 1)FORM 1 MEADOWS.pdf · uploaded 7 Apr 2023Source
- 11 Engineer’s Certificate on Cost Incurred on Project (Form 2)FORM 2 MEADOWS.pdf · uploaded 7 Apr 2023Source
- 3 Engineers Certificate on Quality Assurance (Form 2A FY 2021-22)FORM 2A MEADOWS -3.pdf · uploaded 7 Apr 2023Source
- 4 Engineers Certificate on Quality Assurance (Form 2A FY 2021-22)FORM 2A MEADOWS -4.pdf · uploaded 7 Apr 2023Source
- 8 Disclosure of sold/ booked inventoryINVENTORY MEADOWS.pdf · uploaded 7 Apr 2023Source
- 9 CA Certificate on Project Cost & Fund withdrawal (Form 3)FORM 3 MEADOWS.pdf · uploaded 7 Apr 2023Source
- 1 Annual Audit Report of Statutory CA (Form 5) (FY 2019-20)RERA REPLY 01-31-2023.pdf · uploaded 26 Apr 2023Source
- 2 Copy of Layout Approval (in case of layout)Layout F.pdf · uploaded 17 Jun 2023Source
- 5 Building Plan Approval / NA Order for plotted developmentBuilding Plan 5 F.pdf · uploaded 17 Jun 2023Source
- 6 Building Plan Approval / NA Order for plotted developmentBuilding Plan 7 F.pdf · uploaded 17 Jun 2023Source
- 4 Declaration in FORM Bnotary shiv sir.pdf · uploaded 17 Jun 2023Source
- 9 Disclosure of sold/ booked inventoryRevised Inventory Building 5 and 7.pdf · uploaded 17 Jun 2023Source
- 13 Architect’s Certificate of Percentage of Completion of Work (Form 1)FORM 1 MEADOWS.pdf · uploaded 6 Jul 2023Source
- 12 Engineer’s Certificate on Cost Incurred on Project (Form 2)FORM 2 MEADOWS.pdf · uploaded 6 Jul 2023Source
- 1 Engineers Certificate on Quality Assurance (Form 2A FY 2022-23)FORM 2A CM - 3.pdf · uploaded 6 Jul 2023Source
- 2 Engineers Certificate on Quality Assurance (Form 2A FY 2022-23)FORM 2A CM - 4.pdf · uploaded 6 Jul 2023Source
- 10 Disclosure of sold/ booked inventoryINVENTORY MEADOWS.pdf · uploaded 6 Jul 2023Source
- 10 CA Certificate on Project Cost & Fund withdrawal (Form 3)FORM 3 MEADOWS.pdf · uploaded 6 Jul 2023Source
- 1 Annual Audit Report of Statutory CA (Form 5) (FY 2022-23)Meadows.pdf · uploaded 23 Sep 2023Source
- 14 Architect’s Certificate of Percentage of Completion of Work (Form 1)FORM 1 MEADOWS.pdf · uploaded 7 Oct 2023Source
- 13 Engineer’s Certificate on Cost Incurred on Project (Form 2)FORM 2 MEADOWS.pdf · uploaded 7 Oct 2023Source
- 3 Engineers Certificate on Quality Assurance (Form 2A FY 2022-23)FORM 2A MEADOWS BLDG 03.pdf · uploaded 7 Oct 2023Source
- 4 Engineers Certificate on Quality Assurance (Form 2A FY 2022-23)FORM 2A MEADOWS BLDG 04.pdf · uploaded 7 Oct 2023Source
- 5 Engineers Certificate on Quality Assurance (Form 2A FY 2022-23)FORM 2A MEADOWS BLDG 07.pdf · uploaded 7 Oct 2023Source
- 11 Disclosure of sold/ booked inventoryINVENTORY MEADOWS.pdf · uploaded 7 Oct 2023Source
- 11 CA Certificate on Project Cost & Fund withdrawal (Form 3)FORM 3 MEADOWS.pdf · uploaded 7 Oct 2023Source
- 15 Architect’s Certificate of Percentage of Completion of Work (Form 1)FORM 1 CM.pdf · uploaded 5 Jan 2024Source
- 14 Engineer’s Certificate on Cost Incurred on Project (Form 2)FORM 2 CM.pdf · uploaded 5 Jan 2024Source
- 6 Engineers Certificate on Quality Assurance (Form 2A FY 2022-23)FORM 2A CM3.pdf · uploaded 5 Jan 2024Source
- 7 Engineers Certificate on Quality Assurance (Form 2A FY 2022-23)FORM 2A CM4.pdf · uploaded 5 Jan 2024Source
- 8 Engineers Certificate on Quality Assurance (Form 2A FY 2022-23)FORM 2A CM7.pdf · uploaded 5 Jan 2024Source
- 12 Disclosure of sold/ booked inventoryINVENTORY MEADOWS.pdf · uploaded 5 Jan 2024Source
- 12 CA Certificate on Project Cost & Fund withdrawal (Form 3)FORM 3 CM.pdf · uploaded 5 Jan 2024Source
- 16 Architect’s Certificate of Percentage of Completion of Work (Form 1)FORM 1 CM.pdf · uploaded 5 Apr 2024Source
- 15 Engineer’s Certificate on Cost Incurred on Project (Form 2)FORM 2 CM.pdf · uploaded 5 Apr 2024Source
- 9 Engineers Certificate on Quality Assurance (Form 2A FY 2022-23)FORM 2A CM3.pdf · uploaded 5 Apr 2024Source
- 10 Engineers Certificate on Quality Assurance (Form 2A FY 2022-23)FORM 2A CM4.pdf · uploaded 5 Apr 2024Source
- 11 Engineers Certificate on Quality Assurance (Form 2A FY 2022-23)FORM 2A CM5.pdf · uploaded 5 Apr 2024Source
- 12 Engineers Certificate on Quality Assurance (Form 2A FY 2022-23)FORM 2A CM7.pdf · uploaded 5 Apr 2024Source
- 13 Disclosure of sold/ booked inventoryINVENTORY CM.pdf · uploaded 5 Apr 2024Source
- 13 CA Certificate on Project Cost & Fund withdrawal (Form 3)FORM 3 MEADOWS.pdf · uploaded 5 Apr 2024Source
- 1 Status of Formation of Legal Entity (Society/Co Op etc.)CM 3 SOCIETY CERTIFICATE.pdf · uploaded 13 Jun 2024Source
- 17 Architect’s Certificate of Percentage of Completion of Work (Form 1)CM FORM 1.pdf · uploaded 6 Jul 2024Source
- 16 Engineer’s Certificate on Cost Incurred on Project (Form 2)CM FORM 2.pdf · uploaded 6 Jul 2024Source
- 13 Engineers Certificate on Quality Assurance (Form 2A FY 2022-23)CM 4 FORM 2A.pdf · uploaded 6 Jul 2024Source
- 14 Engineers Certificate on Quality Assurance (Form 2A FY 2022-23)CM 5 FORM 2A.pdf · uploaded 6 Jul 2024Source
- 15 Engineers Certificate on Quality Assurance (Form 2A FY 2022-23)CM 7 FORM 2A.pdf · uploaded 6 Jul 2024Source
- 14 Disclosure of sold/ booked inventoryCM INVENTORY.pdf · uploaded 6 Jul 2024Source
- 14 CA Certificate on Project Cost & Fund withdrawal (Form 3)CM FORM 3.pdf · uploaded 6 Jul 2024Source
- 1 Architect’s Certificate of Percentage of Completion of Work (Form 1)CM FORM 1.pdf · uploaded 6 Oct 2024Source
- 1 Engineer’s Certificate on Cost Incurred on Project (Form 2)CM FORM 2.pdf · uploaded 6 Oct 2024Source
- 1 Engineers Certificate on Quality Assurance (Form 2A FY 2022-23)CM 4 FORM 2A.pdf · uploaded 6 Oct 2024Source
- 1 Engineers Certificate on Quality Assurance (Form 2A FY 2022-23)CM 5 FORM 2A.pdf · uploaded 6 Oct 2024Source
- 1 Engineers Certificate on Quality Assurance (Form 2A FY 2022-23)CM 7 FORM 2A.pdf · uploaded 6 Oct 2024Source
- 1 Disclosure of sold/ booked inventoryCM INVENTORY.pdf · uploaded 6 Oct 2024Source
- 2 Architect’s Certificate of Percentage of Completion of Work (Form 1)CM FORM 1.pdf · uploaded 6 Oct 2024Source
- 2 Engineer’s Certificate on Cost Incurred on Project (Form 2)CM FORM 2.pdf · uploaded 6 Oct 2024Source
- 2 Disclosure of sold/ booked inventoryCM INVENTORY.pdf · uploaded 6 Oct 2024Source
- 7 Engineers Certificate on Quality Assurance (Form 2A FY 2022-23)CM 4 FORM 2A.pdf · uploaded 6 Oct 2024Source
- 8 Engineers Certificate on Quality Assurance (Form 2A FY 2022-23)CM 5 FORM 2A.pdf · uploaded 6 Oct 2024Source
- 9 Engineers Certificate on Quality Assurance (Form 2A FY 2022-23)CM 7 FORM 2A.pdf · uploaded 6 Oct 2024Source
- 1 CA Certificate on Project Cost & Fund withdrawal (Form 3)CM FORM 3.pdf · uploaded 7 Oct 2024Source
- 2 CA Certificate on Project Cost & Fund withdrawal (Form 3)CM FORM 3.pdf · uploaded 7 Oct 2024Source
- 1 Annual Audit Report of Statutory CA (Form 5) (FY 2023-24)Form 5.pdf · uploaded 16 Nov 2024Source
- 1 Annual Audit Report of Statutory CA (Form 5) (FY 2023-24)Form 5.pdf · uploaded 16 Nov 2024Source
- 1 Architect’s Certificate of Percentage of Completion of Work (Form 1)CM FORM 1.pdf · uploaded 6 Jan 2025Source
- 1 Engineer’s Certificate on Cost Incurred on Project (Form 2)CM FORM 2.pdf · uploaded 6 Jan 2025Source
- 1 Disclosure of sold/ booked inventoryCM INVENTORY.pdf · uploaded 6 Jan 2025Source
- 1 Engineers Certificate on Quality Assurance (Form 2A FY 2022-23)CM 4 FORM 2A.pdf · uploaded 6 Jan 2025Source
- 2 Engineers Certificate on Quality Assurance (Form 2A FY 2022-23)CM 5 FORM 2A.pdf · uploaded 6 Jan 2025Source
- 3 Engineers Certificate on Quality Assurance (Form 2A FY 2022-23)CM 7 FORM 2A.pdf · uploaded 6 Jan 2025Source
- 4 Engineers Certificate on Quality Assurance (Form 2A FY 2022-23)CM 4 FORM 2A.pdf · uploaded 6 Jan 2025Source
- 5 Engineers Certificate on Quality Assurance (Form 2A FY 2022-23)CM 5 FORM 2A.pdf · uploaded 6 Jan 2025Source
- 6 Engineers Certificate on Quality Assurance (Form 2A FY 2022-23)CM 7 FORM 2A.pdf · uploaded 6 Jan 2025Source
- 1 CA Certificate on Project Cost & Fund withdrawal (Form 3)Meadows Form 3.pdf · uploaded 7 Jan 2025Source
- 1 Other – TechnicalScan07022025142837 .pdf · uploaded 7 Feb 2025Source
- 1 Architect’s Certificate of Percentage of Completion of Work (Form 1)FORM 1 - MEADOWS.pdf · uploaded 7 Apr 2025Source
- 1 CA Certificate on Project Cost & Fund withdrawal (Form 3)FORM 3 MEADOWS.pdf · uploaded 7 Apr 2025Source
- 1 Engineer’s Certificate on Cost Incurred on Project (Form 2)FORM 2 - MEADOWS.pdf · uploaded 7 Apr 2025Source
- 1 Disclosure of sold/ booked inventoryINVENTORY - MEADOWS.pdf · uploaded 7 Apr 2025Source
- 1 Engineers Certificate on Quality Assurance (Form 2A FY 2022-23)FORM 2A - MEADOWS 5.pdf · uploaded 7 Apr 2025Source
- 2 Engineers Certificate on Quality Assurance (Form 2A FY 2022-23)FORM 2A - MEADOWS 7.pdf · uploaded 7 Apr 2025Source
- 1 Architect’s Certificate of Percentage of Completion of Work (Form 1)FORM 1 CM.pdf · uploaded 7 Jul 2025Source
- 1 CA Certificate on Project Cost & Fund withdrawal (Form 3)FORM 3 CM.pdf · uploaded 7 Jul 2025Source
- 1 Engineer’s Certificate on Cost Incurred on Project (Form 2)FORM 2 CM.pdf · uploaded 7 Jul 2025Source
- 1 Disclosure of sold/ booked inventoryINVENTORY CM.pdf · uploaded 7 Jul 2025Source
- 1 Engineers Certificate on Quality Assurance (Form 2A FY 2022-23)FORM 2A CM 5-7.pdf · uploaded 7 Jul 2025Source
- Form 1MEADOWS FORM 1.pdf · uploaded 9 Jul 2025Source
- Form 2MEADOWS FORM 2.pdf · uploaded 9 Jul 2025Source
- Form 3MEADOWS FORM 3.pdf · uploaded 9 Jul 2025Source
- Disclosure of Sold and Booked InventoryMEADOWS INVENTORY 30-09-2021_20211005_125756.pdf · uploaded 9 Jul 2025Source
- OthersMEADOWS FORM 2A.pdf · uploaded 9 Jul 2025Source
- Form 1FORM 1 MEADOWS.pdf · uploaded 9 Jul 2025Source
- Form 2FORM 2 MEADOWS.pdf · uploaded 9 Jul 2025Source
- Form 3FORM 3 MEADOWS.pdf · uploaded 9 Jul 2025Source
- Disclosure of Sold and Booked InventoryINVENTORY MEADOWS.pdf · uploaded 9 Jul 2025Source
- OthersFORM 2A MEADOWS.pdf · uploaded 9 Jul 2025Source
- Form 1FORM 1 MEADOWS.pdf · uploaded 9 Jul 2025Source
- Form 2FORM 2 MEADOWS.pdf · uploaded 9 Jul 2025Source
- Form 3FORM 3 MEADOWSS.pdf · uploaded 9 Jul 2025Source
- Disclosure of Sold and Booked Inventory31-03-2022 INVENTORY MEADOWS.pdf · uploaded 9 Jul 2025Source
- Othersilovepdf_merged (1).pdf · uploaded 9 Jul 2025Source
- Form 1FORM 1 MEADOWS_compressed (1).pdf · uploaded 9 Jul 2025Source
- Form 2FORM 2 MEADOWS_compressed.pdf · uploaded 9 Jul 2025Source
- Form 3FORM 3 MEADOWS_compressed (2).pdf · uploaded 9 Jul 2025Source
- Disclosure of Sold and Booked InventoryINVENTORY MEADOWS BUILDING 3 - 4_compressed.pdf · uploaded 9 Jul 2025Source
- Othersilovepdf_merged (2).pdf · uploaded 9 Jul 2025Source
- Form 1CM FORM 1.pdf · uploaded 9 Jul 2025Source
- Form 2CM FORM 2.pdf · uploaded 9 Jul 2025Source
- Form 3CM FORM 3.pdf · uploaded 9 Jul 2025Source
- Disclosure of Sold and Booked InventoryCM INVENTORY.pdf · uploaded 9 Jul 2025Source
- OthersCM 3 FORM 2A_merged.pdf · uploaded 9 Jul 2025Source
- Form 1FORM 1 MEADOWS.pdf · uploaded 9 Jul 2025Source
- Form 2FORM 2 MEADOWS.pdf · uploaded 9 Jul 2025Source
- Form 3FORM 3 MEADOWS.pdf · uploaded 9 Jul 2025Source
- Disclosure of Sold and Booked InventoryMEADOWS INVENTORY.pdf · uploaded 9 Jul 2025Source
- Othersilovepdf_merged (3).pdf · uploaded 9 Jul 2025Source
- Form 1FORM 1 MEADOWS.pdf · uploaded 9 Jul 2025Source
- Form 2FORM 2 MEADOWS.pdf · uploaded 9 Jul 2025Source
- Form 3FORM 3 MEADOWS.pdf · uploaded 9 Jul 2025Source
- Disclosure of Sold and Booked InventoryINVENTORY MEADOWS.pdf · uploaded 9 Jul 2025Source
- Othersilovepdf_merged (4).pdf · uploaded 9 Jul 2025Source
- Form 1FORM 1 MEADOWS.pdf · uploaded 9 Jul 2025Source
- Form 2FORM 2 MEADOWS.pdf · uploaded 9 Jul 2025Source
- Form 3FORM 3 MEADOWS.pdf · uploaded 9 Jul 2025Source
- Disclosure of Sold and Booked InventoryINVENTORY MEADOWS.pdf · uploaded 9 Jul 2025Source
- OthersFORM 1 MEADOWS_merged.pdf · uploaded 9 Jul 2025Source
- Form 1FORM 1 MEADOWS.pdf · uploaded 9 Jul 2025Source
- Form 2FORM 2 MEADOWS.pdf · uploaded 9 Jul 2025Source
- Form 3FORM 3 MEADOWS.pdf · uploaded 9 Jul 2025Source
- Disclosure of Sold and Booked InventoryINVENTORY MEADOWS.pdf · uploaded 9 Jul 2025Source
- Othersilovepdf_merged (5).pdf · uploaded 9 Jul 2025Source
- Form 1FORM 1 CM.pdf · uploaded 9 Jul 2025Source
- Form 2FORM 2 CM.pdf · uploaded 9 Jul 2025Source
- Form 3FORM 3 CM.pdf · uploaded 9 Jul 2025Source
- Disclosure of Sold and Booked InventoryINVENTORY MEADOWS.pdf · uploaded 9 Jul 2025Source
- OthersFORM 2A CM4_merged.pdf · uploaded 9 Jul 2025Source
- Form 1FORM 1 CM.pdf · uploaded 9 Jul 2025Source
- Form 2FORM 2 CM.pdf · uploaded 9 Jul 2025Source
- Form 3FORM 3 MEADOWS.pdf · uploaded 9 Jul 2025Source
- Disclosure of Sold and Booked InventoryINVENTORY CM.pdf · uploaded 9 Jul 2025Source
- OthersFORM 2A CM4_merged (1).pdf · uploaded 9 Jul 2025Source
- Form 1CM FORM 1.pdf · uploaded 9 Jul 2025Source
- Form 2CM FORM 2.pdf · uploaded 9 Jul 2025Source
- Form 3CM FORM 3.pdf · uploaded 9 Jul 2025Source
- Disclosure of Sold and Booked InventoryCM INVENTORY.pdf · uploaded 9 Jul 2025Source
- OthersCM 4 FORM 2A_merged.pdf · uploaded 9 Jul 2025Source
- Form 1CM FORM 1.pdf · uploaded 9 Jul 2025Source
- Form 2CM FORM 2.pdf · uploaded 9 Jul 2025Source
- Form 3CM FORM 3.pdf · uploaded 9 Jul 2025Source
- Disclosure of Sold and Booked InventoryCM INVENTORY.pdf · uploaded 9 Jul 2025Source
- OthersCM 5 FORM 2A_merged.pdf · uploaded 9 Jul 2025Source
- Form 1CM FORM 1.pdf · uploaded 9 Jul 2025Source
- Form 2CM FORM 2.pdf · uploaded 9 Jul 2025Source
- Form 3CM FORM 3_compressed.pdf · uploaded 9 Jul 2025Source
- Disclosure of Sold and Booked InventoryCM INVENTORY.pdf · uploaded 9 Jul 2025Source
- OthersCM 5 FORM 2A_merged (1).pdf · uploaded 9 Jul 2025Source
- Form 1FORM 1 - MEADOWS.pdf · uploaded 9 Jul 2025Source
- Form 2FORM 2 - MEADOWS.pdf · uploaded 9 Jul 2025Source
- Form 3FORM 3 MEADOWS.pdf · uploaded 9 Jul 2025Source
- Disclosure of Sold and Booked InventoryINVENTORY - MEADOWS.pdf · uploaded 9 Jul 2025Source
- Othersilovepdf_merged (6).pdf · uploaded 9 Jul 2025Source
- Withdrawal Update Form 1FORM 1 CM.pdf · uploaded 19 Jul 2025Source
- Withdrawal Update Form 1FORM 1 CM.pdf · uploaded 19 Jul 2025Source
- Withdrawal Update Form 2FORM 2 CM.pdf · uploaded 19 Jul 2025Source
- Withdrawal Update Form 2FORM 2 CM.pdf · uploaded 19 Jul 2025Source
- Withdrawal Update Form 3Form 3 -Signed_Comp.pdf · uploaded 19 Jul 2025Source
- Withdrawal Update Form 3Form 3 -Signed_Comp.pdf · uploaded 19 Jul 2025Source
- Withdrawal Update Form 1FORM 1 CM.pdf · uploaded 20 Jul 2025Source
- Withdrawal Update Form 2FORM 2 CM.pdf · uploaded 20 Jul 2025Source
- Withdrawal Update Form 3Form 3 -Signed_Comp.pdf · uploaded 20 Jul 2025Source
- Form 2A (FY 2024-2025)ilovepdf_merged (7).pdf · uploaded 18 Sep 2025Source
- Form 5 (FY 2024-2025)Form 5 Cm.pdf · uploaded 29 Sep 2025Source
- Withdrawal Update Form 1FORM 1 CM.pdf · uploaded 5 Oct 2025Source
- Withdrawal Update Form 1FORM 1 CM.pdf · uploaded 5 Oct 2025Source
- Withdrawal Update Form 2FORM 2 CM.pdf · uploaded 5 Oct 2025Source
- Withdrawal Update Form 2FORM 2 CM.pdf · uploaded 5 Oct 2025Source
- Withdrawal Update Form 3Form 3 -Signed_Comp.pdf · uploaded 5 Oct 2025Source
- Withdrawal Update Form 3Form 3 -Signed_Comp.pdf · uploaded 5 Oct 2025Source
- Form 1FORM 1 CM.pdf · uploaded 6 Oct 2025Source
- Form 2FORM 2 CM.pdf · uploaded 6 Oct 2025Source
- Form 3FORM 3 CM.pdf · uploaded 6 Oct 2025Source
- Disclosure of Sold and Booked InventoryINVENTORY CM.pdf · uploaded 6 Oct 2025Source
- OthersFORM 2A CM.pdf · uploaded 6 Oct 2025Source
- Withdrawal Update Form 1FORM 1 CM.pdf · uploaded 7 Oct 2025Source
- Withdrawal Update Form 2FORM 2 CM.pdf · uploaded 7 Oct 2025Source
- Withdrawal Update Form 3Form 3.pdf · uploaded 7 Oct 2025Source
- Withdrawal Update Form 1CM FORM 1.pdf · uploaded 16 Jan 2026Source
- Withdrawal Update Form 2CM FORM 2.pdf · uploaded 16 Jan 2026Source
- Withdrawal Update Form 3Form 3 Signed.pdf · uploaded 16 Jan 2026Source
- Withdrawal Update Form 1CM FORM 1 Signed.pdf · uploaded 18 Apr 2026Source
- Withdrawal Update Form 2CM FORM 2 Signed.pdf · uploaded 18 Apr 2026Source
- Withdrawal Update Form 3Form 3 Signed_compressed.pdf · uploaded 18 Apr 2026Source
- Withdrawal Update Form 1FORM 1 CM.pdf · uploaded 19 Aug 2026Source
- Withdrawal Update Form 2FORM 2 CM (1).pdf · uploaded 19 Aug 2026Source
- Withdrawal Update Form 3Signed Form 3 CA Certificate.pdf · uploaded 19 Aug 2026Source
- Form 2A (FY 2025-2026)FORM 2A - MEADOWS FY 25-26.pdf · uploaded 21 Aug 2026Source
- Form 5 (FY 2025-2026)Form 5 Signed.pdf · uploaded 22 Sep 2026Source
Technical
- DocumentLayout.pdf · uploaded 25 Feb 2020Source
- Documentbldg 3.pdf · uploaded 25 Feb 2020Source
- Documentbldg 4-compressed.pdf · uploaded 25 Feb 2020Source
- Documentbldg 5.pdf · uploaded 25 Feb 2020Source
- DocumentBldg 7.pdf · uploaded 25 Feb 2020Source
- DocumentLayout F.pdf · uploaded 17 Jun 2023Source
- DocumentBuilding Plan 5 F.pdf · uploaded 17 Jun 2023Source
- DocumentBuilding Plan 7 F.pdf · uploaded 17 Jun 2023Source
- Other – TechnicalScan07022025142837 .pdf · uploaded 7 Feb 2025Source
Technical (Architect)
- DocumentCM FORM 1.pdf · uploaded 6 Oct 2024Source
- DocumentCM FORM 1.pdf · uploaded 6 Oct 2024Source
- DocumentCM FORM 1.pdf · uploaded 6 Jan 2025Source
- DocumentFORM 1 - MEADOWS.pdf · uploaded 7 Apr 2025Source
- DocumentFORM 1 CM.pdf · uploaded 7 Jul 2025Source
- DocumentFORM 1 CM.pdf · uploaded 19 Aug 2026Source
Technical (Engineer)
- DocumentCM FORM 2.pdf · uploaded 6 Oct 2024Source
- DocumentCM FORM 2.pdf · uploaded 6 Oct 2024Source
- DocumentCM FORM 2.pdf · uploaded 6 Jan 2025Source
- DocumentFORM 2 - MEADOWS.pdf · uploaded 7 Apr 2025Source
- DocumentFORM 2 CM.pdf · uploaded 7 Jul 2025Source
- DocumentFORM 2 CM (1).pdf · uploaded 19 Aug 2026Source
Source: Certificates, orders and filings published by MahaRERA. Filings that can't be opened here are listed as they appear on MahaRERA's project page.
Regulatory record
Deedo hasn't found this project's RERA number in any MahaRERA list or order it has read: deregistered, abeyance, NCLT, quarterly-report non-compliance, revoked, regulatory and suo motu orders.
Source: MahaRERA regulatory lists and orders, checked against each RERA number.
Land
In Shahapur (CT), Shahapur taluka
Survey, CTS, gat or plot numbers
Boundaries
- North
- S No 5 And Road
- South
- S No 6 And 7
- East
- S No 9
- West
- S No 6-1
Source: registration certificates and MahaRERA's project page, as stated there.
Professionals
Architects, engineers, chartered accountants and agents named on the registration
| Role | Name | Registration no. |
|---|---|---|
| Chartered accountant | Hitesh Vijay Chawla | — |
| Chartered accountant | Mukesh Nanikram Kishnani | — |
| Chartered accountant | Notnani & Associates | — |
| Engineer | Anilkumar C Shinde | — |
Source: MahaRERA project page. Contact details are not shown.