Ishanya Buildcon
Company or firm · 4 projects · 6 MahaRERA registrations
4Projects6 RERA registrations
0Completedas reported on MahaRERA project pages
100%Kept RERA date5 of 5 past their proposed date, not extended
+0 moMedian delayvs RERA proposed date · 0 extended
0Regulatory casesMahaRERA orders and lists
Projects
Delay is measured against the RERA proposed completion date on the registration certificate.
| Project | Locality | RERA year | Status | Proposed | Revised | Delay |
|---|---|---|---|---|---|---|
| RosewoodP51600027094 | Pimprisado | 2020 | Not reported | 30 Jun 2025 | — | On date |
| RosewoodP51600031092 | Pimprisado | 2021 | Not reported | 31 Dec 2024 | — | On date |
| RosewoodP51600033295 | Pimprisado | 2022 | Not reported | 31 Mar 2025 | — | On date |
| Rosewood-F WingP51600034905 | Pimprisado | 2022 | Not reported | 31 Mar 2025 | — | On date |
| Rosewood G - A Wing & Rosewood H - B WingP51600048687 | Pimprisado | 2023 | Not reported | 31 Dec 2025 | — | On date |
| Rosewood - I J and K WingP51600080593 | Pimprisado | 2025 | Not reported | 31 Dec 2031 | — | On date |
Delivery timeline
RERA proposed completion vs the latest revised date, per registration.
Track record notes
- 5 of 5 registrations whose RERA proposed completion date has passed were never extended beyond it.
- No MahaRERA regulatory order or list names these registrations.
Regulatory cases across projects
None on recordNo MahaRERA deregistration, abeyance, NCLT, revocation or other order names these registrations.
SourcesMahaRERA project pages · registration and extension certificates · regulatory lists and ordersPersonal details of promoters are not shown.Methodology