Impressions
Deedo IDDD-FTSMOf 3 registrations whose promised date has arrived, 1 kept it (33%). The rest ran a median 4 mo late.
Delivery record
5 of 6 registrations with dates moved or missed their RERA date · months late against the original promise
6 registrations with dates · Source: MahaRERA registration and extension certificates
Regulatory cases
No MahaRERA deregistration, abeyance, NCLT, revocation or other order names these registrations.
Projects
Delay is measured against the RERA proposed completion date on the registration certificate; * still open: the date has passed and MahaRERA shows no completion yet.
| Project | Locality | Status | Proposed | Revised | Delay |
|---|---|---|---|---|---|
| Suchit SquareP51700008664 | Dombivli | Completed | 27 Feb 2018 | — | On date |
| ValenciaP51700024879 | Dombivli | Certificate Signed | 31 Mar 2027 | 31 Jul 2027 | +4 mo |
| AmbrinP51700027906 | Dombivli | Certificate Signed | 31 Jan 2023 | 31 Jan 2023 | +46 mo* |
| Ambrin 3P51700078631 | Dombivli | Certificate Signed | 30 Sep 2026 | 30 Jan 2027 | +4 mo |
| Ambrin 2PR1330002501788 | Dombivli | Certificate Signed | 31 Dec 2027 | 30 Apr 2028 | +4 mo |
| Ambrin 4PM1330002600810 | Chole | Certificate Signed | 31 Dec 2030 | 30 Apr 2031 | +4 mo |
Impressions, in questions
Does Impressions finish projects on time?
Of 3 MahaRERA registrations whose promised completion date has arrived, 1 kept it (33%). The rest ran a median 4 mo late. Across Maharashtra, 73% kept their date.
How many projects has Impressions registered with MahaRERA?
6 projects under 6 MahaRERA registrations; 1 completed on MahaRERA.
Does Impressions have MahaRERA regulatory cases?
No MahaRERA deregistration, abeyance, NCLT, revocation or other order names its registrations.