Deedo IDDD-MPFXOf 7 registrations whose promised date has arrived, 6 kept it (86%). The rest ran a median 4 mo late — the same as Maharashtra's 4 mo.
Delivery record
1 of 7 registrations with dates moved or missed their RERA date · months late against the original promise
7 registrations with dates · Source: MahaRERA registration and extension certificates
Regulatory cases
No MahaRERA deregistration, abeyance, NCLT, revocation or other order names these registrations.
Projects
Delay is measured against the RERA proposed completion date on the registration certificate; * still open: the date has passed and MahaRERA shows no completion yet.
| Project | Locality | Status | Proposed | Revised | Delay |
|---|---|---|---|---|---|
| Royal Entrada Phase IIP52100000526 | Wakad | Certificate Signed | 31 Dec 2019 | 31 Dec 2019 | On date |
| Royal MajesticP52100000548 | Rahatani | Certificate Signed | 31 Mar 2018 | 31 Mar 2018 | On date |
| Royal ImpressionsP52100014526 | Bopodi | Certificate Signed | 30 Dec 2020 | 30 Dec 2020 | On date |
| Royal GrandeP52100015350 | Wakad | Certificate Signed | 30 Dec 2022 | 30 Dec 2022 | On date |
| Royal MysticP52100016160 | Rahatani | Certificate Signed | 30 Oct 2021 | 30 Oct 2021 | On date |
| Anp - LandmarkP52100023061 | Wakad | Certificate Signed | 30 Mar 2023 | 30 Mar 2023 | On date |
| Anp MementoP52100026219 | Wakad | Certificate Signed | 30 Sep 2026 | 30 Jan 2027 | +4 mo |
Five Star Construction Company, in questions
Does Five Star Construction Company finish projects on time?
Of 7 MahaRERA registrations whose promised completion date has arrived, 6 kept it (86%). The rest ran a median 4 mo late. Across Maharashtra, 73% kept their date.
How many projects has Five Star Construction Company registered with MahaRERA?
7 projects under 7 MahaRERA registrations; 6 completed on MahaRERA.
Does Five Star Construction Company have MahaRERA regulatory cases?
No MahaRERA deregistration, abeyance, NCLT, revocation or other order names its registrations.