Duville Estates Private Limited
Company or firm · 8 projects · 8 MahaRERA registrations
Projects88 RERA registrations
Completed0as reported on MahaRERA project pages
Kept RERA date71%5 of 7 past their proposed date, not extended
Median delay+0 movs RERA proposed date · 2 extended
Regulatory cases0MahaRERA orders and lists
Projects
Delay is measured against the RERA proposed completion date on the registration certificate.
| Project | Locality | RERA year | Status | Proposed | Revised | Delay |
|---|---|---|---|---|---|---|
| Riverdale Residences-IP52100004692 | Kharadi | 2017 | Not reported | 30 Oct 2022 | 26 Feb 2024 | +16 months |
| Riverdale HeightsP52100008035 | Kharadi | 2017 | Not reported | 28 Feb 2022 | — | On date |
| Riverdale SuitesP52100014163 | Kharadi | 2017 | Not reported | 30 Mar 2023 | 30 Nov 2024 | +20 months |
| Plot A BuildingP52100020853 | Kharadi | 2019 | Not reported | 30 Mar 2022 | — | On date |
| Riverdale GroveP52100029023 | Kharadi | 2021 | Not reported | 30 Jun 2026 | — | On date |
| 30 DriveP52100032106 | Kharadi | 2021 | Not reported | 30 Nov 2023 | — | On date |
| Riverdale AvenueP52100034874 | Haveli | 2022 | Not reported | 15 Oct 2025 | — | On date |
| Riverdale GrandP52100034877 | Kharadi | 2022 | Not reported | 30 Sep 2028 | — | On date |
Delivery timeline
RERA proposed completion vs the latest revised date, per registration.
Track record notes
- 5 of 7 registrations whose RERA proposed completion date has passed were never extended beyond it.
- Longest extension on record: 20 months, for Riverdale Suites (P52100014163).
- No MahaRERA regulatory order or list names these registrations.
Regulatory cases across projects
None on recordNo MahaRERA deregistration, abeyance, NCLT, revocation or other order names these registrations.
SourcesMahaRERA project pages · registration and extension certificates · regulatory lists and ordersPersonal details of promoters are not shown.Methodology