Duville Estates Private Limited

Company or firm · 8 projects · 8 MahaRERA registrations

Projects88 RERA registrations
Completed0as reported on MahaRERA project pages
Kept RERA date71%5 of 7 past their proposed date, not extended
Median delay+0 movs RERA proposed date · 2 extended
Regulatory cases0MahaRERA orders and lists

Projects

Delay is measured against the RERA proposed completion date on the registration certificate.

ProjectLocalityRERA yearStatusProposedRevisedDelay
Riverdale Residences-IP52100004692Kharadi2017Not reported30 Oct 202226 Feb 2024+16 months
Riverdale HeightsP52100008035Kharadi2017Not reported28 Feb 2022—On date
Riverdale SuitesP52100014163Kharadi2017Not reported30 Mar 202330 Nov 2024+20 months
Plot A BuildingP52100020853Kharadi2019Not reported30 Mar 2022—On date
Riverdale GroveP52100029023Kharadi2021Not reported30 Jun 2026—On date
30 DriveP52100032106Kharadi2021Not reported30 Nov 2023—On date
Riverdale AvenueP52100034874Haveli2022Not reported15 Oct 2025—On date
Riverdale GrandP52100034877Kharadi2022Not reported30 Sep 2028—On date

Delivery timeline

RERA proposed completion vs the latest revised date, per registration.

  • Riverdale Residences-I+16 mo
  • Riverdale HeightsOn date
  • Riverdale Suites+20 mo
  • Plot A BuildingOn date
  • Riverdale GroveOn date
  • 30 DriveOn date
  • Riverdale AvenueOn date
  • Riverdale GrandOn date

Track record notes

  • 5 of 7 registrations whose RERA proposed completion date has passed were never extended beyond it.
  • Longest extension on record: 20 months, for Riverdale Suites (P52100014163).
  • No MahaRERA regulatory order or list names these registrations.

Regulatory cases across projects

None on recordNo MahaRERA deregistration, abeyance, NCLT, revocation or other order names these registrations.
SourcesMahaRERA project pages · registration and extension certificates · regulatory lists and ordersPersonal details of promoters are not shown.Methodology