Dnyanraj Madhavrao Sawant
Deedo IDDD-Z3ZMOf 1 registration whose promised date has arrived, 0 kept it (0%). The rest ran a median 61 mo late.
Delivery record
1 of 1 registration with dates moved or missed their RERA date · months late against the original promise
1 registration with dates · Source: MahaRERA registration and extension certificates
Regulatory cases
No MahaRERA deregistration, abeyance, NCLT, revocation or other order names these registrations.
Projects
Delay is measured against the RERA proposed completion date on the registration certificate; * still open: the date has passed and MahaRERA shows no completion yet.
| Project | Locality | Status | Proposed | Revised | Delay |
|---|---|---|---|---|---|
| Sawant PlazaP53100013976 | Sangli Miraj Kupwad (M Corp.) | Certificate Signed | 30 Oct 2021 | 30 Oct 2021 | +61 mo* |
Dnyanraj Madhavrao Sawant, in questions
Does Dnyanraj Madhavrao Sawant finish projects on time?
Of 1 MahaRERA registration whose promised completion date has arrived, 0 kept it (0%). The rest ran a median 61 mo late. Across Maharashtra, 73% kept their date.
How many projects has Dnyanraj Madhavrao Sawant registered with MahaRERA?
1 project under 1 MahaRERA registration; 0 completed on MahaRERA.
Does Dnyanraj Madhavrao Sawant have MahaRERA regulatory cases?
No MahaRERA deregistration, abeyance, NCLT, revocation or other order names its registrations.