Chaphalkar Karandikar Developers
Company or firm · 10 projects · 10 MahaRERA registrations
10Projects10 RERA registrations
0Completedas reported on MahaRERA project pages
100%Kept RERA date4 of 4 past their proposed date, not extended
+4 moMedian delayvs RERA proposed date · 6 extended
0Regulatory casesMahaRERA orders and lists
Projects
Delay is measured against the RERA proposed completion date on the registration certificate.
| Project | Locality | RERA year | Status | Proposed | Revised | Delay |
|---|---|---|---|---|---|---|
| AshokbanP52100027688 | Pune (M Corp.) | 2020 | Certificate Signed | 30 Dec 2023 | 30 Dec 2023 | On date |
| Shashi ApartmentsP52100034852 | Pune (M Corp.) | 2022 | Certificate Signed | 31 Dec 2024 | 31 Dec 2024 | On date |
| Elina LiteP52100035129 | Mohammadwadi | 2022 | Certificate Signed | 31 Jan 2026 | 31 Jan 2026 | On date |
| Aarti ApartmentP52100055822 | Pune (M Corp.) | 2024 | Certificate Signed | 30 Jun 2026 | 30 Jun 2026 | On date |
| ShubhamkarotiP52100077336 | Pune (M Corp.) | 2024 | Certificate Signed | 31 Mar 2027 | 31 Jul 2027 | +4 months |
| Singh ChsP52100079030 | Pune (M Corp.) | 2025 | Certificate Signed | 31 Dec 2028 | 30 Apr 2029 | +4 months |
| DinmaneeP52100079399 | Pune (M Corp.) | 2025 | Certificate Signed | 31 Dec 2027 | 30 Apr 2028 | +4 months |
| PanchratnaPR1260002500550 | Pune (M Corp.) | 2025 | Certificate Signed | 30 Jun 2027 | 30 Oct 2027 | +4 months |
| Rbd- Elina LegendPR1260002502425 | Mohammadwadi | 2026 | Certificate Signed | 31 Dec 2031 | 30 Apr 2032 | +4 months |
| Preetkunj B CHSLPR1260002601144 | Shivajinagar Bhamburda | 2026 | Certificate Signed | 31 Dec 2029 | 30 Apr 2030 | +4 months |
Delivery timeline
RERA proposed completion vs the latest revised date, per registration.
Track record notes
- 4 of 4 registrations whose RERA proposed completion date has passed were never extended beyond it.
- Longest extension on record: 4 months, for Shubhamkaroti (P52100077336).
- No MahaRERA regulatory order or list names these registrations.
Regulatory cases across projects
None on recordNo MahaRERA deregistration, abeyance, NCLT, revocation or other order names these registrations.
SourcesMahaRERA project pages · registration and extension certificates · regulatory lists and ordersPersonal details of promoters are not shown.Methodology