Badhekar Properties
Deedo IDDD-W8V3Of 3 registrations whose promised date has arrived, 1 kept it (33%). The rest ran a median 8 mo late.
Delivery record
4 of 7 registrations with dates moved or missed their RERA date · months late against the original promise
7 registrations with dates · Source: MahaRERA registration and extension certificates
Regulatory cases
No MahaRERA deregistration, abeyance, NCLT, revocation or other order names these registrations.
Projects
Delay is measured against the RERA proposed completion date on the registration certificate; * still open: the date has passed and MahaRERA shows no completion yet.
| Project | Locality | Status | Proposed | Revised | Delay |
|---|---|---|---|---|---|
| MayuraP52100025819 | Kothrud | Certificate Signed | 31 Dec 2026 | 31 Jan 2026 | On date |
| KesharP52100029132 | Kothrud | Certificate Signed | 31 Aug 2027 | 31 Dec 2027 | +4 mo |
| ArunaliP52100030309 | Kothrud | Certificate Signed | 30 Sep 2026 | 30 Sep 2026 | On date |
| SnehP52100034495 | Kothrud | Certificate Signed | 31 Mar 2025 | 31 Dec 2027 | +33 mo |
| ShreekunjaP52100047854 | Karve Nagar | Certificate Signed | 31 Dec 2026 | 31 Jul 2025 | On date |
| SuparnP52100050130 | Erandwana | Certificate Signed | 31 Dec 2025 | 31 Dec 2025 | +11 mo* |
| Harshada Co-Op SocietyP52100050198 | Kothrud | Certificate Signed | 30 Jun 2027 | 30 Oct 2027 | +4 mo |
Badhekar Properties, in questions
Does Badhekar Properties finish projects on time?
Of 3 MahaRERA registrations whose promised completion date has arrived, 1 kept it (33%). The rest ran a median 8 mo late. Across Maharashtra, 73% kept their date.
How many projects has Badhekar Properties registered with MahaRERA?
7 projects under 7 MahaRERA registrations; 1 completed on MahaRERA.
Does Badhekar Properties have MahaRERA regulatory cases?
No MahaRERA deregistration, abeyance, NCLT, revocation or other order names its registrations.