Atharva Developers

Deedo IDDD-NRWE

Of 9 registrations whose promised date has arrived, 0 kept it (0%). The rest ran a median 70 mo late.

Projects99 RERA registrations
Kept RERA date0%Maharashtra: 73%
Median delay70 mowhen late
First sales on record0registered first-sale deeds matched so far
Regulatory cases0none on record

Delivery record

9 of 9 registrations with dates moved or missed their RERA date · months late against the original promise

9 registrations with dates · Source: MahaRERA registration and extension certificates

Regulatory cases

No MahaRERA deregistration, abeyance, NCLT, revocation or other order names these registrations.

Projects

Delay is measured against the RERA proposed completion date on the registration certificate; * still open: the date has passed and MahaRERA shows no completion yet.

ProjectLocalityStatusProposedRevisedDelay
V VastuP52000016373Vadghar (Ct)Certificate Signed30 Sep 202029 Mar 2022+74 mo*
V AawasP52000017224KaranjadeCertificate Signed30 Nov 202029 May 2022+72 mo*
V AarambhP52000017474KaranjadeCertificate Signed31 Jan 202131 Jan 2021+70 mo*
V AashrayaP52000017495Vadghar (Ct)Certificate Signed31 Jan 202130 Jul 2022+70 mo*
V NiwasP52000018180Vadghar (Ct)Certificate Signed30 Nov 202029 May 2022+72 mo*
V AmberP52000018183Vadghar (Ct)Certificate Signed30 Nov 202029 May 2022+72 mo*
LotusP52000020988KaranjadeCertificate Signed15 Dec 202315 Dec 2023+35 mo*
V SankalpP52000024770Vadghar (Ct)Certificate Signed30 Dec 202330 Dec 2023+35 mo*
MannatP52000024771Vadghar (Ct)Certificate Signed30 Dec 202330 Dec 2023+35 mo*

Atharva Developers, in questions

Does Atharva Developers finish projects on time?

Of 9 MahaRERA registrations whose promised completion date has arrived, 0 kept it (0%). The rest ran a median 70 mo late. Across Maharashtra, 73% kept their date.

How many projects has Atharva Developers registered with MahaRERA?

9 projects under 9 MahaRERA registrations; 0 completed on MahaRERA.

Does Atharva Developers have MahaRERA regulatory cases?

No MahaRERA deregistration, abeyance, NCLT, revocation or other order names its registrations.

SourcesMahaRERA project pages · registration and extension certificates · regulatory lists and ordersPersonal details of promoters are not shown.Report a problemMethodology